Safety

Take the necessary and required safety precautions, such as safety nets and lifelines when installing from the 

outside, safety goggles, gloves, hard hat, etc.

Do not step on the glass.

Falling from height
•  When using ladders to go on the roof:

 - 

Ladder in good condition?

 - 

Set up correctly at an angle of 75°?

 - 

Secured below and on top against moving?

 - 

Don’t take heavy material with you on the ladder (3-point contact rule)! If possible, 

     use a crane to lift the material.

•  Do not lift material over the roof edge; use a crane to put the material on the roof.

•  Roof zone: make sure the part of the roof where the skylight/barrel vault will be installed is  

  safe enough, e.g. secure the edge (support system in the roof gutter that supports against the  

  outer wall of the building, with suitable A B C categorie depending on the roof pitch) or use a  

  scaffold so no one can fall off the roof. If the roof is not safe enough, always use a harness with  

  lifeline (adapted to the fall height), attached to a suitable attachment point.

•  Make sure the roof is stable and does not have dangerous openings or insufficient secure parts  

  (e.g. corrugated sheets, …). Take the necessary measures if this is not the case: strengthen,  

  use suitable safety nets below the danger zones, …

•  Before making the roof opening for the skylight/barrel vault: make sure there are safety nets  

  conform to the current legislation. The nets must be attached firmly and sufficiently to the  

 building.

•  When using an aerial work platform: always wear and secure your harness (mandatory)! Leaving  

  the cage is forbidden. 

•  Never walk backwards on a roof, always walk forwards.

•  Make sure there’s enough light in the working zone.

Low-hanging obstacles and falling loads
•  Forbidden to walk under or within a radius of 1 m of a hanging or lifted load.

•  Demarcate the danger zone below the skylight/barrel vault, in the building as well as on the  

  outside near the outer walls (in case material slides off the roof). If the zone is demarcated,  

  people cannot be hit by any falling loads. It’s prohibited to enter these danger zones during  

 construction. 

Crushing hazard
•  All working tools are in good condition, provided with a valid CE label and all necessary safety  

  regulations. These cannot be removed.

•  People who use these working tools are educated for this purpose. Protections are always   

  present on all working tools. They are in good condition and need to be set correctly. 

Tripping/falling
•  Safety is key and it begins with order and tidiness. Clean everything immediately, leave nothing  

  lying around. 

•  Trash needs to be sorted. 

•  Be cautious with electric cables (danger of tripping/falling). Never walk backwards! 

•  Make sure there’s enough light in the working zone.

Содержание Cintralux alu 25 mm

Страница 1: ...BARREL VAULTS Cintralux alu 25 mm Mounting instructions fixed parts for flat curb EN Art N 62822...

Страница 2: ...use suitable safety nets below the danger zones Before making the roof opening for the skylight barrel vault make sure there are safety nets conform to the current legislation The nets must be attache...

Страница 3: ...lose to your body as possible Parts of more than 25 kg must be lifted with at least 2 persons Personal protective equipment Work clothes safety shoes and helmet are mandatory for everyone Lifeline and...

Страница 4: ...p 7 OUTLINE DRAWING OF CINTRALUX ALUMINIUM 25 MM FIXED PARTS FLAT CURB p 8 ASSEMBLY SEQUENCE OF FIXED PARTS CINTRALUX ALUMINIUM 25 MM FLAT CURB p 8 ASSEMBLY OF CINTRALUX ALUMINIUM 25 MM FIXED PARTS F...

Страница 5: ...e agreed dimensions must be strictly observed Height above finished roof min 200 mm Min finished thickness 65 mm Max finished thickness 100 mm The top flange and the curb must share the same thickness...

Страница 6: ...whether the top is flat and smooth Clean it in advance if necessary and remove sawdust irregularities etc Tighten a rope on both sides of the curb or use lasers Find the average position of the curb...

Страница 7: ...nt 15 x 15 mm LP525 Bottom arch LP025 Finishing profile LP502 Top arch LP512 Side top arch LP726 End piece retainer profile VPGDGL Arch stabiliser Accessories 46577 Bracket for flat curb 36187 Screw w...

Страница 8: ...m arch 5 Arch stabilisers 6 Multi walled PC panel 25 mm Aluminium top arch PC cellular sheet 25 Aluminium bottom arch Aluminium lateral profile Aluminium end cap Aluminium lateral profile Roof claddin...

Страница 9: ...red size 1 cm play will be provided between the curb and the bottom profile end piece Aligning 2 Lateral profile Position the lateral profiles for flat curb LP125 at the location of the long sides Lay...

Страница 10: ...nector 46580 which is already clamped in the lateral profiles The connector also ensures a play of 5 mm 2 mm between the lateral profiles Seal the seams between the lateral profiles LP125 so that wate...

Страница 11: ...er panels the distance between the brackets will be less than where full sheet widths are to come 4 Bottom arch Place the pre bent bottom arch LP525 at the location of bracket 46577 and tighten using...

Страница 12: ...from both sides of PC panel SPC25X6 just before assembly and place the multi walled 25 mm PC panel with the UV side facing upwards There are three types of PC panels 25 mm X6 full panel widths 1050 mm...

Страница 13: ...panel with the finishing profile LP025 to the other lateral profile LP125 Clips Full panel widths 1050 mm are always used with the exception of the outer edges of the barrel vault towards the end piec...

Страница 14: ...t fasten too tightly Wait a moment with placing the side top arches LP512 which will come at the ends of the barrel vaults 8 End piece retainer sheet Place the multi walled PC end piece retainer sheet...

Страница 15: ...ps of the bottom profile end piece LP725 on the 25 mm PC end piece retainer sheet Remove the PC end piece retainer sheet 25 mm once more and saw it off at the saw line PC 25 mm end piece retainer shee...

Страница 16: ...is in the same way for the other end of the barrel vault 9 End piece retainer profile Now place the end piece retainer profile LP726 on top of the sawn off PC end piece retainer sheet Do this in the s...

Страница 17: ...iece 47471 fits over the bracket 4657 Tighten the bolts Do this in the same way for the other end of the barrel vault Depending on the assembly on one or the other end of the barrel vault the left or...

Страница 18: ...pening parts of the Cintramax and on the fixed parts of the barrel vault At minimum this maintenance includes cleaning of the sheets with water and a light PH neutral soap All fastenings must be check...

Страница 19: ...ure that the tape has not been damaged during assembly There is no warranty for dust inclusion UV side and scratches always mount the multi layered sheets with the UV protective side facing up This su...

Страница 20: ...56 20 00 00 F 32 0 56 21 95 99 INFO SKYLUX BE WWW SKYLUX BE ONLY USE ORIGINAL PARTS SUPPLIED BY SKYLUX FAILURE TO USE ORIGINAL PARTS VOIDS THE GUARANTEE THESE GUIDELINES ARE ONLY ADVISORY IN NATURE T...

Отзывы: