![Siemens SIMOSEC Скачать руководство пользователя страница 71](http://html.mh-extra.com/html/siemens/simosec/simosec_operating-instructions-manual_382508071.webp)
832-6063.0 * OPERATION SIMOSEC * REVISION 02
71
Operation
18
To be observed for operation
Before operation, always verify readiness for service of the panels to be operated.
18.1
Verification of readiness for service
The
"
ready-for-service
"
indicator for SF
6
gas shows the gas density in the three-position
switch required to operate the panel.
If a three-position switch filled with SF
6
gas is not ready for operation:
• Do not put the switchgear into operation
• Do not operate the switchgear
• Contact the Siemens Service Operation.
18.2
Verification of safe isolation from supply of a feeder
Verify safe isolation from supply of the switchgear or the panel:
• with the voltage indicator of the capacitive voltage detection system
Fig. 56:
Ready-for-service indicator for SF
6
gas
a
Indication of operating state
s
Green area: Panel ready for operation
d
Red area: Panel not ready for operation
DO NOT