Installing the panels
If required, the actions described in this section must be repeated until all panels are
bolted together.
In the operations described in the following sections, it is assumed that
• the transport units are installed starting either from the left or right.
• a new switchgear unit or group is being installed which has not been connected to a
source of power yet, and that it is therefore not energized.
12.1
Installing the end wall
There must not be any partition wall between the end wall and the frame of the end
panel. Partition walls are only used to separate individual panels, respectively the cable
compartments (see Fig. 37: Bolted joint of panels, page 47). The end panels are shipped
from the factory without partition wall, except for group orders without a specified panel
configuration. In this case, remove the partition wall before starting installation.
Installing left end wall
Ö
Align the end wall with the panel frame.
Ö
Secure the end wall to the frame of the panel with the bolts provided.
Installing right end wall
The right end wall is mounted in a similar manner.
Fig. 33:
Fixing points of left end wall
a
Left end panel
s
Frame of end panel
d
Left end wall
f
Fixing points
g
Screw with contact washer