![Siemens SIMOSEC Скачать руководство пользователя страница 69](http://html.mh-extra.com/html/siemens/simosec/simosec_operating-instructions-manual_382508069.webp)
832-6063.0 * INSTALLATION SIMOSEC * REVISION 02
69
Installation
16.8
Connecting operating voltage (high voltage)
The connection is conditional on complete and trouble-free commissioning
Ö
Switch all switching devices to "OPEN" position.
Ö
Ground cable feeders without connected high voltage cables at the feeder, and
secure the grounding switch against de-grounding (opening).
Ö
Verify correct terminal-phase connections with respect to next incoming feeder:
• Apply operational high voltage to opposite substation.
• Connect phase comparison test unit (e.g., make Pfisterer, type EPV) to the capaci-
tive test sockets of one phase at the panel and at the adjacent panel.
• Test all three phases using phase comparitor.
Ö
Connect tested incoming feeder (bus bars / feeders) according to the specifications /
the instructions of the switchgear owner.