Installation
56
REVISION 02 * INSTALLATION SIMOSEC * 832-6063.0
13.3
Installing cold shrink insulation at cable connections
Determine the length of the
cold shrink
Ö
Measure the distance between the second skirt of the bushing type insulator and a
reference-point, e. g., the middle of the lower hole in the cable connection terminal,
and note the distance.
Ö
Measure the distance between the upper edge of the cable termination and a
reference-point, e. g., the middle of the lower hole in the cable lug and note the
distance.
NOTE!
Before installing, read the supplier’s documentation of the cold shrink insulation.
NOTE!
Before installing, the cold shrink insulation should be at room temperature. If the
cold shrink insulation is installed while cold, the material may not contract (shrink)
fully.
Ö
Before installing, bring the cold shrink insulation up to room temperature.