Installation, connecting up, commissioning
3.3 Note on operation
CP 1243-1
36
Operating Instructions, 04/2017, C79000-G8976-C365-03
Requirement: Configuration prior to commissioning
One requirement for the commissioning of the module is the completeness of the STEP 7
project data (see below, step 5).
Installing, connecting up and commissioning the module
Note
Connection with power off
Only wire up the S7-1200 with the power turned off.
Table 3- 2
Procedure for installation and connecting up
Step
What to do
Notes and explanations
1
Mount the CP on the DIN rail and connect it to
the module to its right.
Use a 35 mm DIN rail.
The slots to the left of the CPU are permitted.
2
Secure the DIN rail.
3
Connect the Ethernet cable to the CP.
You will find the pinout of the interface in the section Technical
4
Turn on the power supply.
5
The remaining steps in commissioning involve
downloading the STEP 7 project data.
The STEP 7 project data of the CP is transferred when you
load to the station. To load the station, connect the engineer-
ing station on which the project data is located to the Ethernet
interface of the CPU.
You will find more detailed information on loading in the follow-
ing sections of the STEP 7 information system:
•
"Loading project data"
•
"Using online and diagnostics functions"
6
Close the front covers of the module and keep
them closed during operation.
3.3
Note on operation
NOTICE
Closing the front panels
To ensure interference-free operation, keep the front panels of the module closed during
operation.
Содержание CP 1243-1
Страница 10: ...Table of contents CP 1243 1 10 Operating Instructions 04 2017 C79000 G8976 C365 03 ...
Страница 116: ...Configuration 4 12 Access to the Web server CP 1243 1 116 Operating Instructions 04 2017 C79000 G8976 C365 03 ...
Страница 140: ...Dimension drawings CP 1243 1 140 Operating Instructions 04 2017 C79000 G8976 C365 03 Figure B 2 From above ...