Chapter 6) 7SR23 DAD Commissioning & Maintenance Guide
©2013 Siemens Protection Devices Limited
Chapter 6 Page 20 of 26
It is also desirable to check the operating voltage achieved with the setting resistor and all parallel CTs connected
but de-energised. A higher capacity test set will be required for this test. Adequate current must be supplied to
provide the magnetising current of all connected CTs.
Precautions should be taken to ensure that no personnel are at risk of contact with any of the energised
secondary wiring during the test and that the high impedance external components are adequately thermally
rated.
Settings Data:
Voltage Setting (V
S
)
V
S
Measured
Settings Data:
Operate Current (I
OP
)
I
OP
Measured
CT50
To complete testing of the differential protection it is required to primary inject current through CTs to simulate an
out of zone fault and ensure stability of the relay.
The test can then be repeated with one set of CT secondary connections reversed to prove operation at the
correct primary operate current.
3.2.1.1 Element Blocking
The differential elements can be blocked by Binary Input Inhibit or from the CT supervision (CT50) function.
Where applied this functionality should be checked.
Element BI
Inhibits Checked CT
Supervision
(CT50) Checked
CT50
Check correct indication, trip output, alarm contacts, waveform record.
Check that any shorting links are removed after testing.
Содержание 7SR23 DAD
Страница 1: ...Answers for energy 7SR23 DAD High Impedance Protection Relay Reyrolle Protection Devices ...
Страница 2: ......
Страница 4: ...7SR23 DAD Contents 2013 Siemens Protection Devices Limited ...
Страница 40: ...Chapter 1 7SR23 DAD Description Of Operation 2013 Siemens Protection Devices Limited Chapter 1 Page 36 of 36 ...
Страница 60: ...Chapter 3 7SR23 DAD Performance Specification 2013 Siemens Protection Devices Limited ...
Страница 78: ...Chapter 3 7SR23 DAD Performance Specification 2013 Siemens Protection Devices Limited Chapter 3 Page 20 of 20 ...
Страница 80: ...Chapter 4 7SR23 DAD Data Communications 2013 Siemens Protection Devices Limited Chapter 4 Page 2 of 54 ...
Страница 134: ...Chapter 5 7SR23 DAD Installation Guide 2013 Siemens Protection Devices Limited Chapter 5 Page 2 of 24 ...
Страница 156: ...Chapter 5 7SR23 DAD Installation Guide 2013 Siemens Protection Devices Limited Chapter 5 Page 24 of 24 ...
Страница 158: ...Chapter 6 7SR23 DAD Commissioning Maintenance Guide 2013 Siemens Protection Devices Limited Chapter 6 Page 2 of 26 ...
Страница 182: ...Chapter 6 7SR23 DAD Commissioning Maintenance Guide 2013 Siemens Protection Devices Limited Chapter 6 Page 26 of 26 ...
Страница 184: ...Chapter 7 7SR23 DAD Applications Guide 2013 Siemens Protection Devices Limited Chapter 7 Page 2 of 42 ...
Страница 224: ...Chapter 7 7SR23 DAD Applications Guide 2013 Siemens Protection Devices Limited Chapter 7 Page 42 of 42 ...
Страница 225: ......