Operation & Maintenance Manual
──
LG968 /969Wheel Loader
72
the bucket tilt forward or backward to shake down the material.
z
After dumping, use the bucket to level equipment. Rear tilt bucket to level position,
operate the
working equipment control
handle to let the lift arm lower down to prepare for next operation.
(5)
Pushing Operation
Level the bucket to the ground, push accelerograph to
move forward, if there is block during moving, raise the
lift arm a little and move forward continuously. When
operate the lift arm to lift the or lower, operate the control
lever between lifting and lowering operating.
Never
let
the lever at the raising or lowering position to ensure
pushing smoothly.
(6)
Strickling Operation
Tilt the bucket to the bottom to let the blade touch the
ground. For hard ground, let the working equipment
control handle at the float position; for soft ground, let
the lift arm control lever at the
neutral
position.
Use
Reverse
transmission to strickle the ground.
(7)
Towing Operation
△
!
NOTICE
Watch the Torque Converter Oil Temperature Gauge all the
time during pushing. If the temperature is too high, stop to let
machine to cool down and then continue to work.