Coupling Instructions
The couplings on the ends of the pre-charged line sets are self-sealing when installed properly.
Follow these instructions carefully.
These steps must be performed by an EPA Certified Type II or higher technician.
Initial Connections
1. Remove the protector caps and plugs. Wipe the seats and threaded surfaces with a clean
cloth to remove any possible foreign matter.
2. Lubricate the inside of the couplings, especially the O-rings, with refrigerant oil.
3. Position the fittings on the correct connections on the condenser and ice machine.
•
The 1/2" discharge line (schrader valve end) goes to the remote condenser fitting marked
“discharge line”.
•
The 3/8" liquid line (schrader valve end) goes to the remote condenser fitting marked
“liquid line”.
•
The 1/2" discharge line goes to the ice maker fitting marked “discharge line”.
•
The 3/8" liquid line goes to the ice maker fitting marked “liquid line”.
Final Connections:
4a. Begin by tightening the couplings together by hand until it is certain that the threads are
properly engaged.
4b. Then using two wrenches tighten the coupling until it bottoms out or a definite increase in
resistance is felt.
It is important that ONLY the nut on the pre-charged tube be turned, or the diaphragms will be
torn out by the piercing knives and they will be loose in the refrigeration system. Note: As the
couplings are tightened, the diaphragms in the quick connect couplings will begin to be
pierced. As that happens, there will be some resistance to tightening the swivel nut.
4c. Continue tightening the swivel nut until it bottoms out or a very definite increase in
resistance is felt (no threads should be showing).
5. Use a marker or pen to mark a line on the coupling nut and unit panel. Then tighten the
coupling nut an additional one-quarter turn. The line will show the amount that the nut turns.
Do NOT over tighten.
6. After all connections have been made, and after the receiver valve has been opened (open
at Initial Start Up), check the couplings for leaks.
September 2006 Page 16
General Installation - Remote
Содержание C0522SR-1
Страница 96: ...Wiring Diagram C0522R C0530R C0630R C0830R C1030R Single Phase after 9 09 September 2009 Page 96 ...
Страница 98: ...Wiring Diagram C0522R C0530R C0630R C0830R C1030R Three Phase after 9 09 September 2009 Page 98 ...
Страница 126: ...Wiring Diagram C0630R 6 C0830R 6 C1030R 6 September 2009 ...
Страница 127: ...Wiring Diagram C0830R 63 C1030R 63 September 2009 ...