Smoking

 

 

chimney draught not sufficient

 

 
 

check chimney’s permeability 
and its parameters  (see tab. 
height and section to boiler’s 
power, p. 10), check if chimney 
end is not lower than roof ridge

 

gases channels dirty

 

 

clean up boiler through 
washout door

 

sealing rope indoor and 
washout openings worn

 

replace a rope (to be replaced

 

regularly)

 

improper assembly of boiler 
and chimney connection

 

check accurateness

 

 

very low atmospheric pressure

   

improper position of smoke 
throttle to current chimney 
draught 

adjust sprocket position if it is 
closed to much  

too much ash gathered on the 
fumes whirling elements 

Clean both fumes whirlin 
elements and fumes channel 
with boiler’s tools 

Sudden 
temperature 
and pressure 
rise

 

installation valves closed

 

open the valves

 

 

pressure vessel frozen

 

heat the pressure vessel

 

Water licking 
out of boiler 

so called “boiler’s sweating”, 
this is natural process caused 
by temperature difference in 
boiler

 

during boiler’s start-up and 
after each standby "heat the 
boiler" e.g. burn it up to 70°C  
and keep that temperature for 
several hours

 

“Hitting, 
shooting” in 
boiler

 

 

air in the heating installation 
and  
boiler due to improperly 
performed  
filling in process (see chapter  
7.1, p. 8) 

 

 

"heat the boiler" e.g. burn it up 
to70°C  and keep that 
temperature  
for a longer time, till the whole 
air  
is removed from boiler remove  
the  air  from  installation by  
opening  the  valves  on 
radiators. 

 

 

 

 

 

 

 

Содержание UWG

Страница 1: ...CUMENTATION of water boiler s for heating installations SAS UWG type adopted for black coal combustion of nut coal SAS UWG Z A K A D M E T A L O W O K O T L A R S K I 28 100 Busko Zdr j Owczary ul Prz...

Страница 2: ...r to a chimney 7 6 4 Connecting boiler to a chimney installation 8 7 Operation and installation guidelines 8 7 1 Filing with water 8 7 2 Boiler s firing up 9 Table technical exploitation parameters 10...

Страница 3: ...3...

Страница 4: ...ection Boilers are specifically recommended for the flats heating in single family homes pavilions etc where calculated feeding water temperature does not exceed 85 C and working pressure does not exc...

Страница 5: ...or boilers SAS UWG above 17 kW for boilers up to 14 kW the washout door and load door make up one unit pos 5 6 for boiler s convection channels cleaning In the upper convection section of the boiler t...

Страница 6: ...ical Start Up Documentation 6 1 REQUIREMENTS FOR BOILER ROOM The boiler room where the heating boiler for central heating installation shall be installed must conform the requirements of detailed regu...

Страница 7: ...ed chimney draught of min 0 12 0 30 mbar see tab p 10 point 9 Selection of the chimney s height and section comparing to boiler power should be based on detailed regulations being in force in the coun...

Страница 8: ...ion NOTE It is recommended to connect the boiler to heating system provided with three or four pass valve The main advantage of such connection is boiler protection function against low temperature co...

Страница 9: ...and wood Then thin layer of coal is applied Once the batch of coal is glowing ash box and furnace door should be closed Open fuel load door and fill the combustion chamber with fuel up to the lower ed...

Страница 10: ...5 205 220 260 300 330 9 Required chimney draught mbar 0 30 10 Maximal allowable opperating pressure bar 1 5 11 Maximal allowable working temp C 85 12 Reccomended heating water working temp C 60 80 13...

Страница 11: ...blowdown connection 3 water jacket 10 air intake dosage flap 16 hot water connector pipe 22 thermometer 4 furnace chamber 11 water grates 17 smoke conduit 5 6 washout fuel load door 12 cast iron grate...

Страница 12: ...wdown connection 3 water jacket 10 air intake dosage flap 16 hot water connector pipe 22 thermometer 4 furnace chamber 11 water grates 17 smoke conduit 5 washout door 12 cast iron grates movable 18 sm...

Страница 13: ...ior each boiler s fire up process but not less than after 150 260 of boiler s continuous work Cleaning of convection channels with volatile ashes residues should be performed every 3 7 days depending...

Страница 14: ...its damage all defects of boiler should be immediately removed NOTE The boiler should be regularly cleansed from soot and tarry residues any residue on the convection channels walls disrupts proper h...

Страница 15: ...lements Clean both fumes whirlin elements and fumes channel with boiler s tools Sudden temperature and pressure rise installation valves closed open the valves pressure vessel frozen heat the pressure...

Страница 16: ...ating installation make check if all boiler s components are in good working condition and that the boiler is fully equipped NOTE Boilers need to be transported in the vertical position In order to re...

Страница 17: ...ometer 5 Warranty does not cover consumable items sealant rope 6 Manufacturer is obligated to carry out the charge free repair under warranty in time period of 14 days starting from the date of applic...

Страница 18: ...mentation however basic described properties of the product shall be maintained Any remarks and questions on boiler s SAS type exploitation shall be addressed ZAK AD METALOWO KOTLARSKI Owczary ul Prze...

Страница 19: ...19 SERVICE REPAIRS...

Страница 20: ...mperature boiler of SAS UWG type installed and operated in pursuance of Technical Start Up Documentation Boiler no Heating capacity Heated surface Year of manufacture Manufacturer signature and stamp...

Отзывы: