- 13 - 

 

 
 
 
 

6.1. FILING WITH WATER 

 

Boiler  and  the  entire  installation  water  filling  is  to  be  performed  using  blowdown 
connection. 

 

This  activity  should  be  performed  slowly  allowing  the  air  residing  in  the  
installation  to  be removed. 
It  is  accomplished  when water  is  going  out  of  overflow  pipe.  When  filling  the  
heating  system  installation with water it is recommended to loose screw connection 
at  the  place  of  boiler  –  installation  assembly  (on  the  hot  water  connector).    Once 
water is flowing out, tight the connection. 

 

NOTE: Filling installation  with  water when boiler  is  in  use,  especially  if  it  is  
very hot  is strictly forbidden, as boiler’s damage or  fracture may be caused. 

 

Once  heating  season  is  over  do  not  get  rid  of  water  from  heating  installation  and 
boiler. When  required,  water may  be  let of  through blowdown  connection to a drain 
once it is cooled down. 

 

 

6.2. FIRING UP AND OPERATE A BOILER 

 

Before fuel fire – up it is mandatory to check installation filling with water. Water can’t 

be  frozen.  It  must  be  checked  also  if  there  is  no  water  leakage  on  boiler  or  screw 

joints. Before first boiler start – up chimney must be burned.

 

 
Person who servicing boiler must be aware about that some boilers surfaces 
are hot and before touching it is mandatory to wear protective gloves! 
Safety goggles also should be used. 

 

6.2.1. 

FIRING UP AND FUNCTIONING OF A BOILER IN THE  AUTOMATIC MODE 

 

The  boiler  works  in  the  continuous  mode  –  without  shopping  the  fire,  so  firing  out 

operations  are  pretty  seldom.  Before  the  boiler  is  faired  up,  the  hopper  should  be 

supplied with fuel (fuel bunker) however, in such amount that the cover may be easily 

closed. While loading the hopper, make sure that stones, metal elements, etc. are not 

present  in  the  bulk  of  fuel.  Otherwise,  screw  feeder  mechanism  may  be  blocked. 

Then the controller should be switched on MANUAL MODE  (

in this mode, feeder  

6.  OPERATION AND EXPLOITATION GUIDELINES

 

 

Содержание MULTI Series

Страница 1: ...M E T A L O W O K O T L A R S K I 28 100 Busko Zdr j Owczary ul Przemys owa 3 Phone 48 41 378 46 19 Fax 48 41 370 83 10 TECHNICAL START UP DOCUMENTATION of water boilers for heating installations SAS...

Страница 2: ...tallation 15 6 Operation and exploitation guidelines 16 6 1 Filling with water 16 6 2 Firing up and functioning of a boiler 16 6 2 1 Firing up and functioning of a boiler in automatic mode 17 6 2 2 Fi...

Страница 3: ...3...

Страница 4: ...ater temperature does not exceed 85 C and working pressure does not exceed 1 5 bar Required gases draught pressure after a boiler is 0 30 0 45 mbar depending on boiler s power These boilers may also w...

Страница 5: ...in the temperature set on the controller The controller constantly measures the temperature of water boiler Depending on the results it controls fuel feeder and ventilator At the same time the control...

Страница 6: ...arge cleaning door pos 6 furnace door pos 11 and ash box door pos 13 are placed on the boiler s front For periodic cleaning operations and also for firing up a boiler the retort may be accessed throug...

Страница 7: ...1200 1280 A1 mm 290 290 305 305 330 330 B mm 1110 1235 1235 1300 1300 1300 B1 mm 450 535 535 605 605 605 H mm 1430 1430 1490 1490 1590 1590 H1 mm 1300 1300 1375 1375 1475 1475 H2 mm 980 980 1050 1050...

Страница 8: ...door 14 air intake dosage flap 15 air draft regulator 16 connecting strip 17 hot water connector pipe 18 upper washout hole cover 19 smoke conduit clearing hole 20 smoke throttle 21 smoke conduit 22...

Страница 9: ...tent to 10 Ash melting temperature 1150 C Low coal swelling coal should not tend to stick when burner Volatile particles content 30 40 It is recommended to use coal which is prone to agglomeration cok...

Страница 10: ...allation shall be installed must conform the requirements of detailed regulations being in force at the country of destination e g PN 87 B 02411 In particular the following requirements shall be fulfi...

Страница 11: ...k draught may also cause or help in carbon black forming which is then settling down on the boiler s convection channels If the draught is too strong it will cause excessive air to draw into the retor...

Страница 12: ...system provided with three or four pass valve The main advantage of such connection is boiler protection function against low temperature corrosion preventing it from premature wear If not satisfacto...

Страница 13: ...d down 6 2 FIRING UP AND OPERATE A BOILER Before fuel fire up it is mandatory to check installation filling with water Water can t be frozen It must be checked also if there is no water leakage on boi...

Страница 14: ...as varying fuel quality may cause the boiler to burn out If the fire is out during up phase the furnace should be cleaned and boiler s channels ventilated and the whole starting procedure must be rep...

Страница 15: ...ve At the same time the controller operates the heating system circulation pump if such is provided Heat requirement in the heat installation is varying due to changing outdoor conditions such as the...

Страница 16: ...t those adverse phenomena should go away During normal exploitation of boiler in the traditional combustion mode burning process is based on periodic refueling Single load of basic fuel is sufficient...

Страница 17: ...of burned fuel and apply cleaning and conservation of the entire boiler Pay special attention to lubricate inner partitions of combustion chamber and all movable elements with oil For the period of br...

Страница 18: ...ection channels walls disrupts proper heat transfer from the exchanger lowering this way an efficiency of device and increases fuel consumption 6 6 OPERATE AND MAINTENACE OF A FEEDER AND RETORT Feeder...

Страница 19: ...nstallation improper functioning of controller or fan adjust controller s settings up to weather conditions or quality of fuel mainly feeder operation time and fuel delivery pauses should be changed t...

Страница 20: ...oal reduce the set of fuel supply by 5 10 or increase blow in power Wait 20 30 minutes until such changes come to effect what should be deflected in change of fire state In order to ensure the failure...

Страница 21: ...arried out by authorized team Before connecting a boiler to a heating installation make check if all boiler s components are in good working condition and that the boiler is fully equipped NOTE Boiler...

Страница 22: ...on alterations made by user or other third parties will cause the warranty to be invalid 8 Application of reclamation should be addressed at manufacturer 9 Boiler replacement realized by manufacturer...

Страница 23: ...umentation however basic described properties of the product shall be maintained Any remarks and questions on boiler s SAS type exploitation shall be addressed ZAK AD METALOWO KOTLARSKI Owczary ul Prz...

Страница 24: ...24 SERVICE REPAIRS...

Страница 25: ...25 SERVICE REPAIRS...

Страница 26: ...perature boiler of SAS MULTI type installed and operated in pursuance of Technical Start Up Documentation Boiler no Heating capacity Heated surface Year of manufacture Manufacturer signature and stamp...

Отзывы: