Setting  may  be  adjusted  no  more  than  5  –  10  %  in  a  single  approach.  It  takes 

approximately  20 – 30 min., until the effect of changes will be visible. 

If we allow the retort to work with high excess of air in the longer time comparing to 

volume of delivered fuel, it will result in the fire “moving down” into the bottom of the 

retort, what in consequence may cause cast iron nozzles to be damaged. 

Avoid also retort to work with too thick layer of fuel. 

When in the automatic mode, the controller measure water temperature in boiler, and 

based on its value, controls fuel feeder and blow-in fan, making optimal setting for the 

specific fuel type. 

As  far  as  weather  condition  are  concerned,  combustion  intensity,  regulation  and 

heating  capacity  of  the  boiler  should  be  accommodated  following  changing 

conditions. This is done by readjusting the temperature of water coming out of boiler 

(when  tree-way,  or  four-way  valve  is  installed,  the  control  functions  is  made  by 

changing the position of the gate valve). At the same time, the controller operates the 

heating system circulation pump (if such is provided). 

Heat  requirement  in  the  heat  installation  is  varying  due  to  changing  outdoor 

conditions  such  as  the  day  time  and  outdoor  temperature.  Temperature  of  water 

coming out of boiler depends also on the building thermal characteristic, construction  

materials used, especially those used for insulation. 

During fire up phase smoke may be getting out of boiler into room or sweating of the 

boiler may be observed. After boiler and fluke is warmed up, these effects should be 

out.  Boiler’s  operation  stoppage  may  be  due  to  getting  rid  of  fuel  in  the  hopper,  or 

feeder blockage due to hard object, stones, etc. presence.   

 

6.2.2. 

FIRING UP AND FUNCTIONING OF A BOILER IN THE  

          

“TRADITIONAL” MODE 

 

Before firing up  takes place,  ash box door should be fully opened,  but fuel loading  

door and washout hole door should be fully closed. In order to prevent  gases against 

moving it back into the fuel bunker, while the traditional mode is on (fuel combustion 

on the water  grate),  it  is  recommended  to  partially  fill the fuel bunker with fine  

coal,    and  then  in  the  manual  mode  several  cycles  of  feeder  work  should  be 

practiced.  

Содержание MULTI Series

Страница 1: ...M E T A L O W O K O T L A R S K I 28 100 Busko Zdr j Owczary ul Przemys owa 3 Phone 48 41 378 46 19 Fax 48 41 370 83 10 TECHNICAL START UP DOCUMENTATION of water boilers for heating installations SAS...

Страница 2: ...tallation 15 6 Operation and exploitation guidelines 16 6 1 Filling with water 16 6 2 Firing up and functioning of a boiler 16 6 2 1 Firing up and functioning of a boiler in automatic mode 17 6 2 2 Fi...

Страница 3: ...3...

Страница 4: ...ater temperature does not exceed 85 C and working pressure does not exceed 1 5 bar Required gases draught pressure after a boiler is 0 30 0 45 mbar depending on boiler s power These boilers may also w...

Страница 5: ...in the temperature set on the controller The controller constantly measures the temperature of water boiler Depending on the results it controls fuel feeder and ventilator At the same time the control...

Страница 6: ...arge cleaning door pos 6 furnace door pos 11 and ash box door pos 13 are placed on the boiler s front For periodic cleaning operations and also for firing up a boiler the retort may be accessed throug...

Страница 7: ...1200 1280 A1 mm 290 290 305 305 330 330 B mm 1110 1235 1235 1300 1300 1300 B1 mm 450 535 535 605 605 605 H mm 1430 1430 1490 1490 1590 1590 H1 mm 1300 1300 1375 1375 1475 1475 H2 mm 980 980 1050 1050...

Страница 8: ...door 14 air intake dosage flap 15 air draft regulator 16 connecting strip 17 hot water connector pipe 18 upper washout hole cover 19 smoke conduit clearing hole 20 smoke throttle 21 smoke conduit 22...

Страница 9: ...tent to 10 Ash melting temperature 1150 C Low coal swelling coal should not tend to stick when burner Volatile particles content 30 40 It is recommended to use coal which is prone to agglomeration cok...

Страница 10: ...allation shall be installed must conform the requirements of detailed regulations being in force at the country of destination e g PN 87 B 02411 In particular the following requirements shall be fulfi...

Страница 11: ...k draught may also cause or help in carbon black forming which is then settling down on the boiler s convection channels If the draught is too strong it will cause excessive air to draw into the retor...

Страница 12: ...system provided with three or four pass valve The main advantage of such connection is boiler protection function against low temperature corrosion preventing it from premature wear If not satisfacto...

Страница 13: ...d down 6 2 FIRING UP AND OPERATE A BOILER Before fuel fire up it is mandatory to check installation filling with water Water can t be frozen It must be checked also if there is no water leakage on boi...

Страница 14: ...as varying fuel quality may cause the boiler to burn out If the fire is out during up phase the furnace should be cleaned and boiler s channels ventilated and the whole starting procedure must be rep...

Страница 15: ...ve At the same time the controller operates the heating system circulation pump if such is provided Heat requirement in the heat installation is varying due to changing outdoor conditions such as the...

Страница 16: ...t those adverse phenomena should go away During normal exploitation of boiler in the traditional combustion mode burning process is based on periodic refueling Single load of basic fuel is sufficient...

Страница 17: ...of burned fuel and apply cleaning and conservation of the entire boiler Pay special attention to lubricate inner partitions of combustion chamber and all movable elements with oil For the period of br...

Страница 18: ...ection channels walls disrupts proper heat transfer from the exchanger lowering this way an efficiency of device and increases fuel consumption 6 6 OPERATE AND MAINTENACE OF A FEEDER AND RETORT Feeder...

Страница 19: ...nstallation improper functioning of controller or fan adjust controller s settings up to weather conditions or quality of fuel mainly feeder operation time and fuel delivery pauses should be changed t...

Страница 20: ...oal reduce the set of fuel supply by 5 10 or increase blow in power Wait 20 30 minutes until such changes come to effect what should be deflected in change of fire state In order to ensure the failure...

Страница 21: ...arried out by authorized team Before connecting a boiler to a heating installation make check if all boiler s components are in good working condition and that the boiler is fully equipped NOTE Boiler...

Страница 22: ...on alterations made by user or other third parties will cause the warranty to be invalid 8 Application of reclamation should be addressed at manufacturer 9 Boiler replacement realized by manufacturer...

Страница 23: ...umentation however basic described properties of the product shall be maintained Any remarks and questions on boiler s SAS type exploitation shall be addressed ZAK AD METALOWO KOTLARSKI Owczary ul Prz...

Страница 24: ...24 SERVICE REPAIRS...

Страница 25: ...25 SERVICE REPAIRS...

Страница 26: ...perature boiler of SAS MULTI type installed and operated in pursuance of Technical Start Up Documentation Boiler no Heating capacity Heated surface Year of manufacture Manufacturer signature and stamp...

Отзывы: