3.
Observe the movement of the force-displacement transmis-
sion device and the position of the contact blade on the mast
disconnector and check whether the contact blade reaches
its end positions securely.
When the end position is reached, you
should hear an audible clicking in the Trac-
Feed
®
SFA.
6.6.2 Electrical measurements and function tests
In the context of commissioning of the TracFeed
®
SFA, electrical
function tests have to be carried out from the control room.
In accordance with the IEC 60364-6-61 (DIN VDE 0100-610), the
following electrical measurements and tests have to be carried out
before
the function test:
n
Measurement of the control cables’ grid loop impedance
‘Measurement of the grid loop impedance’ on page 51
n
Measurement of the insulation resistance between the wires of
a control cable and against the earthing potential
‘Measurement of the insulation resistance’ on page 52
n
Measurement of the earthing resistance
‘Measurement of the earthing resistance’ on page 53
n
Documentation of the measurements
Assembly
Final checks > Electrical measurements and function tests
14.09.2022
TracFeed
®
SFA Electromechanical remote motor drive
50
Содержание 3EGF020333
Страница 72: ...Appendix Appendix 14 09 2022 TracFeed SFA Electromechanical remote motor drive 72...
Страница 89: ......
Страница 90: ...Rail Power Systems GmbH 2022...