Rockwell Automation Publication 750-IN118A-EN-P - May 2021
45
Chapter
3
Mechanical and Electrical Installation
Perform the steps in this chapter after the steps in
. The installation of the configured bays and other components of the
PowerFlex® 755T Drives Configured to Order Program consists of the
following principal tasks:
•
Unpack the product and prepare it for installation
•
Mechanically install the bays
•
If your product includes multiple shipping sections, make the electrical
interconnections between the bays that are part of different shipping
sections
•
Make the electrical connections to the input power supply and motor
(
)
Perform the steps in this chapter in the order listed:
Remove Side and Top
Packaging
If there is any packaging on the sides and top of the shipping section, remove
it. Packaging may include plastic wrapping and a wood crate. Save any
documentation packaged in the plastic wrapping.
Topic
Page
Remove Detached Installation Hardware
Remove Shipping Skid and Cleats
Prepare Bay Interiors for Installation
Attach Floor Mounting Hardware to the Bays
Place an Additional Bay Into the Lineup
Place the IP54, UL Type 12 Roof Assemblies
Secure Floor Mounting Hardware to the Floor
Make Bay-to-Bay Electrical Connections
For this step, use the information in the following
sections:
Electrical Connections Made to Each Configured
Component and Connection Locations