Ember Installation Guide: 12890-F 06-21
Commissioning
The commissioning sheet, and a 19 mm small
spanner for the gas connection, is located in a plastic
pouch inside the unit on top of the PCB cover.
Follow the commissioning instructions to complete
the gas pressure checks. When commissioning is
complete check for full and correct operation of the
appliance, and return the commissioning sheet to its
plastic pouch.
The gas pressures must be checked against those printed on the data plate of the appliance. The
pressures are factory set and may not require adjustment. When checking the operating pressures
the combustion chamber glass must be on.
Commissioning sheet (and small 19 mm
spanner) located on top of the PCB cover
Inlet pressure test point screw
Pilot pressure adjustment screw
(manometer position)
Pilot pressure test point screw
Main burner pressure test point screw