58
12V wiring
In this section, we will show the basic 12V and 24V connections for off-grid systems that use a
PWM- type controller. Please follow them thoroughly.
Caution!
The battery must first be wired to the charge controller before the solar
panel is connected to the charge controller.
6.1 Battery to charge controller
The battery(s) must first be connected to the charge controller before proceeding to any other
connections. Most PWM Controllers have automatic battery voltage detection, and the controller
must detect what voltage level it will be charging at.
Figure 6.1
Charge controller connected to a 12V battery
Before starting the connection, keep in mind the following:
The charge controller should be as close as possible to the batteries. This helps keep line
loss to a minimum level.
Remember to always use the recommended gauge size based on the PV system and
charge controller.
NEC maximum current for different copper wire sizes
AWG
16
14
12
10
8
6
4
2
0
Max.
Current
10A 15A 20A 30A 55A 75A 95A 130A 170A
Содержание Off-Grid Kit
Страница 8: ...8 Wiring 1 Unscrew battery terminals and connect battery connections...
Страница 10: ...10 4 Insert battery remote sensor block terminal and connect wires POLARITY SENSITIVE...
Страница 16: ...16...
Страница 17: ...17 Repeat for each Z Bracket in the set at each corner...
Страница 18: ...18...
Страница 20: ...20...
Страница 21: ...21 NOTE Orient panel in level plumb layout as desired before fixing in position...
Страница 23: ...23 Repeat for all brackets NOTE Seal around all edges of bracket and screws...
Страница 26: ...26 NOTE Mark all holes locations in this step as the panel must be removed for well nut insertion...
Страница 27: ...27...
Страница 29: ...29 NOTE Orient panel in level plumb layout as desired before fixing in position...
Страница 30: ...30 Repeat for all fasteners NOTE Screw has compressed and expanded the well nut binding into the roof material...
Страница 36: ...36 NOTE Start lag bolt threading by hand...
Страница 37: ...37 Rail System Construction 2 1...
Страница 38: ...38 4 3...
Страница 39: ...39 6 5...
Страница 40: ...40 Repeat for all continuous rail sets Rail Seating 7 1...
Страница 41: ...41 3 2...
Страница 42: ...42 5 4...
Страница 43: ...43 Panel Securement WARNING End clamps must be installed a minimum of 1 30 mm from the rail edges 6 1...
Страница 44: ...44 3 2...
Страница 45: ...45 5 4 NOTE Ensure that the End Clamp is spaced a minimum distance of 1 25 from rail end face...
Страница 46: ...46 Continue mid clamp procedure for each additional panel 6 7...
Страница 55: ...55 Figure 7 Figure 8...