12 Checklist for Commissioning and Testing
1.
Check the polarity and level of the auxiliary voltage before powering up the IPC402x.
2.
Connect to IPC402x via the Ethernet or USB interface. Log in as
config
or
admin
.
3.
Open the
Site
manager
subtab
.
4.
Test binary inputs by applying 24 VDC at one input at a time. Verify that:
a.
The correct LED on the unit lights up.
b.
The corresponding LED symbol in the
Site manager
is activated.
c.
Corresponding indication message is sent via the selected remote interface.
5.
Check
Enable
Manual control of outputs
box in
Site manager
. If required, disconnect the
outputs from external objects. Verify that:
a.
The correct LED on the unit lights up when activated in
Site manager
.
b.
The correct output is activated. Measure the resistance across the output on
terminal block. It should be < 1 Ohm when the relay is active.
c.
If possible, activate the output via the remote interface.
6.
If the station is in operation, the phase currents connected and with a measurable current,
check that:
a.
The correct amplitude is displayed in the
Site manager
.
b.
The currents are symmetrically presented in
Site manager
. If the amplitudes are
equal and the residual current near 0 is safe, the connection is correct.
c.
Create a disturbance file and check that the phase sequence is the expected one.
d.
Measurement values are displayed correctly in the remote control center.