TECHNICAL MANUAL MT044
35
7.1
GENERAL
Periodical inspection and maintenance shall be carried out according to the regulations in force (kind and
frequencies). Before carrying out any operation it is important to ascertain that the regulator has been cut off both
upstream the regulator and the on/off valves.
The maintenance operations are closely associated with the quality of the gas transported (impurities, humidity,
gasoline, corrosive substances) and with the efficiency of the filtering.
Preventive maintenance should be carried out at intervals which, if not established by regulations in force, depend
on:
- the quality of the gas transported;
- the cleanliness and conservation of the piping upstream from the regulator: in general, for example, when
starting the equipment for the first time, more frequent maintenance is required because of the precarious state
of cleanliness inside the piping;
- the level of reliability required from the regulation system.
Before starting the disassembly operations on the apparatus you should check that:
- a set of recommended spares is available. The spares must be original
Fiorentini
ones, bearing in mind
that the more important ones such as diaphragms are marked
- A set of wrenches is available as specified in table 11.
For a proper maintenance the reccomended spare parts are unequivocally identified by labels indicating:
- The No of assembly drawing SR of the apparatus for which the spare parts are suitable,
- The position showed in the assembly drawing SR of the apparatus
N.B. The use of non-original spare parts relieves us of all responsibilities.
In the maintenance is carried out by your own authorized personnel, we reccomend putting reference markings,
before the disassembly, on those parts which could have directional or reciprocal positioning problems when
reassembling. Finally, we would remind you that O-Rings and sliding mechanical components (rods, etc.) must be
lubricated, before the re-assembly, with a fine
layer
of silicone grease. Before recommissioning of equipment after
maintenance, external tightness shall be verified at appropriate pressure to assure no external leakage. When
equipment is used as safety accessory to PED, internal sealing shall be verified at appropriate pressure to assure
the internal sealing at the maximum expected operating pressure. Both verifications are essential to assure safe
use at foreseen operating conditions; they have, anyhow, to comply with the national regulations in force.
7.0 MAINTENANCE
Содержание NORVAL
Страница 2: ...TECHNICAL MANUAL MT044 2 Inlet pressure Outlet pressure NORVAL Issue February 2003 ...
Страница 4: ...4 ...
Страница 8: ...8 ...
Страница 10: ...TECHNICAL MANUAL MT044 10 5 Pe 4 1 3 2 74 Pa Fig 1 ...
Страница 36: ...TECHNICAL MANUAL MT044 36 7 2 NORVAL REGULATOR MAINTENANCE PROCEDURE Fig 17 ...
Страница 39: ...TECHNICAL MANUAL MT044 39 7 3 NORVAL REGULATOR I N MAINTENANCE PROCEDURE Fig 18 ...
Страница 43: ...TECHNICAL MANUAL MT044 43 7 4 MAINTENANCE PROCEDURE FOR THE NORVAL REGULATOR I N ER Fig 19 ...
Страница 50: ...TECHNICAL MANUAL MT044 50 9 0 LIST OF RECOMMENDED SPARE PARTS ...
Страница 51: ...TECHNICAL MANUAL MT044 51 NORVAL pression regulator ...
Страница 58: ...TECHNICAL MANUAL MT044 58 NOTES ...
Страница 59: ...TECHNICAL MANUAL MT044 Ordering Information Part No PFN375DN50 40 PFN375DN50 45 ...