A.  

Confi rm the opening is plumb and level.

 

Note: It is critical that the bottom is level.

B. 

 

Confi rm the door will fi t the opening. 

Measure 

all four sides of the opening to make sure it is 3/4" 
larger than the door in width and 1/2" larger in height. 
Measure the width at the top, bottom, and center. 
Measure the height at the far left side, the far right 
side, and in the center.

Note: 1-1/2" or more of solid wood blocking is 
required around the perimeter of the opening. 
Fix any problems with the rough opening before 
proceeding.

C. 

Cut the water resistive barrier.

1

ROUGH OPENING PREPARATION

Interior 

1A

Interior 

1B

Exterior

1D

UIDVU

.BLFBDVUVQGSPN

FBDIUPQDPSOFSBUB

P

BOHMFUPBMMPXUIFXBUFS

SFTJTUJWFCBSSJFSUPCFMBQQFE

PWFSUIFmOBUUIFIFBEPG

UIFEPPS

TUDVU

OEDVU

SEDVU

8BUFS3FTJTUJWF#BSSJFS

$

D. 

Fold the water resistive barrier.

 Fold side fl aps into the 

opening and staple to inside wall. Fold top fl ap up and 
temporarily fasten with fl ashing tape.

For Doors Using Optional Sill Pan Go To Step 1I. 

E. 

Apply sill fl ashing tape #1. 

Cut a piece of fl ashing tape 12" 

longer than the opening width. Apply at the bottom of the 
opening as shown (1E) so it overhangs 1" to the exterior.

Note: The tape is cut 12" longer than the width so that it 
will extend 6" up each side of the opening.

F. 

Tab the sill fl ashing tape and fold. 

Cut 1" wide tabs at 

each corner (1/2" from each side of corner) (1F). Fold tape 
to the exterior and press fi rmly to adhere it to the water 
resistive barrier.

G. 

Apply sill fl ashing tape #2.

 Cut a piece of fl ashing tape 

12" longer than the opening width. Apply at the bottom, 
overlapping tape #1 by at least 1". 

DO NOT

 allow the tape to 

extend past the interior face of the framing (1G).

 

In-swing doors:

 If the wall depth is greater than 5", add a 

third piece of fl ashing tape. The fl ashing tape should come to 
within 1" of the interior face of the framing.

Note: The fl ashing tape may not fully cover the 
framing members. 

1F

1"

1/2"

1/2"

6"

1E

£

H. 

Attach the aluminum sill support or wood blocking 

to the 

exterior of the box plate to support the edge of the door sill. 
Place the sill support fl ush with the subfl oor.

1H

DOORS •

 ALL

 DOORS •

 ALL

 DOORS •

 ALL

 DOORS •

 ALL

 DOORS •

 ALL

 DOORS •

 ALL

 DOORS

GO TO STEP 2

Содержание 818K0100

Страница 1: ...her construction methods multiple units or bow and bay windows may be obtained from Pella Corporation or a local Pella retailer or by visiting http www pella com Building designs construction methods...

Страница 2: ...ers 2 Phillips with 8 shaft and small at blade T20 Torx Wrench Drill Drill bits 13 64 and 1 8 and masonry bit for concrete applications INSTALLATION CLIP OPTION 6 or 8 installation clips 6 x 5 8 corro...

Страница 3: ...Apply sill ashing tape 1 Cut a piece of ashing tape 12 longer than the opening width Apply at the bottom of the opening as shown 1E so it overhangs 1 to the exterior Note The tape is cut 12 longer tha...

Страница 4: ...g tape to the width of the opening Install to the anges of the sill pan and overlap the tape from step 1N by 1 If needed add a second or third piece of ashing tape until the sill pan is covered to the...

Страница 5: ...ons for Performance Upgrade and HurricaneShield product requires additional clip installation or screw installation Clip installation prep is included in Step 2B Screw installation steps are included...

Страница 6: ...of sealant Place the rst bead of sealant 1 2 from the base of the interior sill pan lip This bead should also continue up the corner of the sill pan at each end sealing the vertical joints of the sil...

Страница 7: ...ly open the door s and remove all shipping spacers Note Be sure to remove the spacers from the bottom edge of the door panel Use the construction handle to operate both the active and passive door pan...

Страница 8: ...the open screw hole Make sure the screw passes through the shims and into the structural framing M Check door operation Open and close the door to check for proper operation Make sure the door will l...

Страница 9: ...oximately 8 from the top of the door frame head Insert a 8 x 3 screw provided into the pilot hole making sure it passes through the shim and into the rough opening framing Note This step does not appl...

Страница 10: ...rough opening in the locations shown On hinge jambs clearance hole locations are centered between hinges Hinge Jambs See 5A In Swing diagram upper right Fixed and Lock jambs diagram for placement of t...

Страница 11: ...nufacturers s recommendations NOTE Not required on In swing Fixed doors Out Swing SILL HEAD Drill 1 8 diameter pilot holes through the clearance hole in the frame 5C 10 x 3 1 2 corrosion resistant woo...

Страница 12: ...into the space between the door and the rough opening and apply a 1 deep bead of foam This will allow room for expansion of the foam and will minimize squeeze out Apply sealant across the interior sur...

Страница 13: ...s with window and door materials and voids Limited Warranty For additional information on nishing see the Pella Owner s Manual or go to www pella com EXTERIOR FINISHING Wood doors require painting imm...

Страница 14: ...management of moisture within the wall systems The determination of the suitability of all building components including the use of Pella products as well as the design and installation of ashing and...

Страница 15: ...This page left blank intentionally...

Страница 16: ...This page left blank intentionally...

Отзывы: