Testing
5-7
7976-A2-GB20-10
August 1998
Send and Monitor 511
The LTU initiates the test by sending a command to the remote unit to send a
511 test pattern. When the remote unit detects the command, it sends a
511 pattern and lights the front panel test LED. Each unit will send and monitor
the 511 pattern. The duration and results of the test are displayed on the Network
Test screen of each unit.
NOTE:
The send and monitor test is not a loopback test. Each unit independently
sends and monitors a 511 pattern.
CAP
G.703
Port
CAP
E1
LIU
Framer
Framer
Transceiver
98-16002
CAP
CAP
E1
LIU
Framer
Framer
Transceiver
AIS
AIS
511
Gen
511
Gen
511
Pattern
511
Pattern
511
Gen
511
Gen
"
Procedure
To run a Send and Monitor 511 test:
1. Position the cursor at the Start command next to Send and Monitor 511 on
the Network Tests screen.
2. Press Enter.
The Start command is changed to Stop.
3. To manually stop the test, verify that the cursor is positioned at the Stop
command.
4. Press Enter.
When a Send and Monitor 511 test is active, a count of bit errors is displayed next
to the test duration, and the ResetMon virtual function key is available for use.
Type r or R or select the ResetMon virtual function key to reset the error count.
Содержание Hotwire 7976
Страница 42: ...Initial Startup and Configuration 3 18 7976 A2 GB20 10 August 1998 This page intentionally left blank...
Страница 56: ...Monitoring the Unit 4 14 7976 A2 GB20 10 August 1998 This page intentionally left blank...
Страница 66: ...Testing 5 10 7976 A2 GB20 10 August 1998 This page intentionally left blank...
Страница 78: ...Security 7 6 7976 A2 GB20 10 August 1998 This page intentionally left blank...
Страница 104: ...Standards Compliance for SNMP Traps B 6 7976 A2 GB20 10 August 1998...
Страница 112: ...Technical Specifications D 2 7976 A2 GB20 10 August 1998...