2. BitStorm 1900 Installation and Testing
2-100
BitStorm 1900 Installation and Maintenance Guide
1900-A2-GN20-00
Task 016: Testing Data Connectivity
This procedure checks data connectivity from the customer premise
distribution frame and the BitStorm 1900 shelf.
Requirements
A StormPort Modem with power adapter and extension cord (if
necessary) is required for this procedure.
Step
Procedure
1.)
Identify the data connections being tested at the EtherLoop cross-
connect block and the Modem card on the BitStorm 1900 shelf.
2.)
Install and connect the modems on the corresponding lines at the
customer premises locations.
3.)
Connect power to the modem.
4.)
Turn on the BitStorm 1900.
5.)
Observe the modem and BitStorm 1900 Modem card LEDs. After
about 4-5 minutes, all LEDs at both the BitStorm 1900 and CPE
locations should be green, with the transfer LEDs flickering.
STOP
<RXKDYHFRPSOHWHGWKLVWDVN
Содержание BitStorm IP DSLAM 1900
Страница 1: ...BitStorm 1900 IP DSLAM Installation and Maintenance Guide Document No 1900 A2 GN20 00 July 2002...
Страница 12: ...List of Tables viii BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...
Страница 16: ...About This Document xii BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...
Страница 48: ...1 BitStorm 1900 IP DSLAM 1 32 BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...
Страница 148: ...Appendix B Cabling Specifications B 132 BitStorm 1900 Installation and Maintenance Guide 1900 A2 GN20 00...