2.5. Installing filters
At renovation sites, flush and clean the existing heating system.
A filter should always be installed on both the heating circuit return line and the brine
circuit return line before the heat pump.
Install a shut-off valve on both sides of the filter to facilitate easy
cleaning and replacing of the filter element.
2.6. Connecting to cooling systems
If the brine circuit is laid into boreholes, the collector circuit can also be used for cooling
the house. If the brine circuit is laid in surface soil or in water, it is not recommended to
connect it to a cooling system, as the soil and water temperature usually rises to such
levels that there is not much cooling capacity in the brine.
Take a separate branch from the brine circuit’s return line and lead it to an air-
conditioner with integrated cooling radiator or to a cooling radiator placed in separate
air intake duct. Install a separate circuit for the cooling radiator, equipped with own
rotary pump, see figure below.
GSHP26 ver. 4
A
fan
B
cooling radiator
C
filter
D
circulation pump
E
regulating valve
F
non-return valve
G
ground circuit return line
H
shut-off valves
For more detailed information in connecting to air conditioner,
refer to the manufacturer’s instructions.
Содержание RE 110
Страница 2: ......
Страница 45: ...RE03 1406 EN 43 48 WIPL02 ver 1 Figure1 Wilo IPL 50 115 0 75 2...
Страница 46: ...44 48 RE03 1406 EN WIPL01 ver 1 Figure2 Wilo IPL 50 120 1 5 2 and Wilo IPL 50 130 2 2 2...
Страница 47: ...RE03 1406 EN 45 48 WSP03 ver 1 Figure3 Wilo Stratos Para 25 1 7...
Страница 51: ......
Страница 52: ...www oilon com...