6 Start-up and regulation
Preparations
Filling the DHW heater
at HK 200S / HK 200S-6
1. Check whether the switch in the SMO control
module is in the position „ ”.
2. Check whether the drain valve has been com-
pletely closed, and whether the temperature lim-
iter has not been activated (F3).
3.
Compatible NIBE air/water heat pumps have
been listed in the Connection Options section.
1. Open the hot water tap in the building.
2.
Open the valve cutting off cold water. When doing
so, the valve should be completely open.
3.
When water starts to flow out of the hot water tap,
DHW heater is full and the tap can be closed.
1. Open the vent at the top point of the heating sys-
tem.
2. Set all the isolation valves in the position allowing
for flow in all circuits.
3.
Open the valve for filling the heating installation
and fill it with the heating medium.
4.
Close the vent when the heating medium flows
out of it continuously (without air bubbles).
5. Control the manometer showing pressure in-
crease. Fill the system until the pressure of 2 bar,
and then close the filling valve.
6. Start the circulation pump of the heating system
every now and then, while opening the vents
placed on the heating circuit.
7. Open the safety valve until the pressure at the
manometer falls down to about 1 bar of the nor-
mal operating range.
8. If, while venting, the pressure drops down below
1 bar, supplement the heating medium in the cir-
cuit.
Filling and venting
Filling and venting the heating system
and HK 200S / HK 200S-6