22
ATTACHING THE MOTOR TO THE
MAIN TROLLEY
Assemble the motor to the main trolley using
5/16” x 1” bolts, flat washers, lock washers,
and nuts. Use the top set of holes on the motor
mounts. See Figure 18.
Keeping the hub oriented upward, assemble
the 3.2” motor pulley to the motor shaft. Use
the key that’s supplied with the motor. Do not
tighten set screw just yet.
Figure 19 shows the correct motor configura
-
tions for two-auger, three-auger, and four-auger
machines. After attaching the motor to the main
trolley, repeat the process for the remaining trol-
leys.
On all motors with two leads, secure the female
lead to the spacer with wire ties. Then connect
the female lead to the male lead of the next mo-
tor.
Figure 17C. Draft Link and Chain Assembly—Detail 2
Correct Draft Link Installation
Wrong Draft Link Installation
The chain must be installed
correctly or the draft link will
collide with the sprocket.
Содержание STIR-RITE
Страница 23: ...23 Figure 18 Main Trolley Assembly Main Trolley Motor Mount 3 2 Motor Pulley Beam...
Страница 24: ...24 Cord Connections to Motors Figure 19 Cord Connections to Single or Multiple Down Augers...
Страница 45: ...45 APPENDIX...
Страница 46: ...46 Stir Rite System General Overview...
Страница 48: ...48 This page is intentionally left blank...
Страница 49: ...49 REPLACEMENT PARTS...
Страница 52: ...52 Stir Rite System Pivot Assembly...
Страница 54: ...54 Stir Rite System Main Trolley...
Страница 56: ...56 Stir Rite System Auxiliary Trolley...