NV20LT/NV15LT INSTALLATION MANUAL
COMMISSIONING
PAGE 2.9.2
VERSION 4.0 2018-02-26
Pre-Commissioning Tasks
1.
Terminate the transmitter's RF output into a precision, 50
, resistive dummy load that is
adequately rated for the maximum expected total power output.
2.
Verify that all panels are installed, and that their attaching hardware is firmly tightened.
3.
Verify all program inputs are connected to the back of the controller and optional exciter.
4.
Close the external interlock (if installed). If an external interlock is not installed, simulate the
closing of the external interlocks by applying a short circuit between TB1-1 and TB1-2 of the
optional remote interface PWB (A16), if installed. If the remote interface PWB is not installed,
apply a short circuit between pins 19 and 20 of the
REMOTE I/O-A (A1J2A)
connector on the rear
of the controller (A4).
NOTE
: An interlock jumper (Nautel Part # 211-5060) is provided in the NV20LT/NV15LT’s ancillary kit. It
is intended to plug directly into the
REMOTE I/O-A (A1J2A)
connector (pins 19 and 20), on the rear of
the controller module (A4) or into the
INTLK
inputs (TB1-1 and 2), on the optional remote interface
PWB (A16), if installed. This jumper cannot be used if you are using a D-sub connector to make other
remote I/O connections. Instead, you must solder a jumper between pins 19 and 20 of the mating
connector (Nautel Part # JS28, also provided in the ancillary kit).
5.
Set the switch on the front of each RF power module to its
ENABLE
position.
WARNING! If a jumper is placed between the INTLK inputs [pins 19 and 20
of the controller’s REMOTE I/O-A connector (A1J2A) or TB1-1 and 2 on the
optional remote interface PWB], safety features controlled by the external
interlocks will be disabled. A fail-safe method of alerting personnel to this
fact should be implemented. Voltages which are dangerous to life will be
present on the RF output stages and the antenna system if the transmitter
is turned on.
Содержание NV20LT
Страница 2: ......
Страница 4: ......
Страница 8: ...NV20LT NV15LT INSTALLATION MANUAL PAGE 2 VIII VERSION 4 0 2018 02 26...
Страница 18: ...NV20LT NV15LT INSTALLATION MANUAL UNPACKING AND POSITIONING PAGE 2 2 8 VERSION 4 0 2018 02 26...
Страница 26: ...NV20LT NV15LT INSTALLATION MANUAL INSTALLING OPTIONS PAGE 2 3 8 VERSION 4 0 2018 02 26...
Страница 30: ...NV20LT NV15LT INSTALLATION MANUAL CONNECTING TO STATION REFERENCE GROUND PAGE 2 4 4 VERSION 4 0 2018 02 26...
Страница 36: ...NV20LT NV15LT INSTALLATION MANUAL CONNECTING AC POWER PAGE 2 5 6 VERSION 4 0 2018 02 26...
Страница 42: ...NV20LT NV15LT INSTALLATION MANUAL INSTALLING PROGRAM INPUTS PAGE 2 7 4 VERSION 4 0 2018 02 26...
Страница 48: ...NV20LT NV15LT INSTALLATION MANUAL INSTALLING CONTROL MONITOR WIRING PAGE 2 8 6 VERSION 4 0 2018 02 26...
Страница 60: ...NV20LT NV15LT INSTALLATION MANUAL COMMISSIONING PAGE 2 9 12 VERSION 4 0 2018 02 26...
Страница 64: ...NV20LT NV15LT INSTALLATION MANUAL PARTS AND TOOLS PAGE 2 10 4 VERSION 4 0 2018 02 26...