3.0
Installation and Commissioning
22
GenStar MPPT
23
Read Block
instructions
before joining
to GenStar
board
2
1
4
3
Figure 3-5. ReadyBlock Installation - refer to separate Block documentation for complete instructions
STEP 1:
OPEN any load disconnects or breakers, and turn OFF any loads.
STEP 2:
Connect positive and negative wires to the load, and to any load bus bars or load panel
terminals.
STEP 3:
Install a correctly sized load/output breaker or fused disconnect switch in the OPEN position
located near the load output terminals of the controller.
STEP 4:
Connect the positive and negative load wires (either directly, or from a junction) to the
GenStar load terminals.
DO NOT CLOSE ANY LOAD DISCONNECTS OR BREAKERS AT THIS TIME.
3.4.7 READYBLOCK INSTALLATION
For complete documentation
,
refer to each Ready Block's installation and operation
instructions.
As seen in Figure 2-1, and then as described in Section 2.3:
A. Loosen screw (7)
B. Remove the cover (9) by pressing in the tabs (10)
C. Use a knife to cut out the dead panels (8) for each corresponding block being installed
BMS BLOCK NOTES:
Only one BMS Block is supported per system. If multiple BMS blocks are present, a system alarm will trigger and a
status message will indicate which of the BMS blocks is active for collecting data from a BMS-battery
FURTHER:
• When using a BMS block, only a single battery (or a bank of parallel batteries) is supported in a network
of host controllers.
• When using a BMS block, only a single manufacturer of batteries is supported. If the battery-bank is
changed to a new manufacturer, the user only needs to change the battery configuration type for the
BMS block.
• When using a BMS block, only a single battery model is supported. If a network of parallel
batteries is employed, to work properly with the BMS block, all of the batteries must be of the
same model.