MONGOOSE PRO Shale Shaker
14
Field Installation and Operation Manual 9092F02001AENG (D)
14
9.3
Removing Packaging Material
The MONGOOSE PRO is always secured for transportation with integrated shipping brackets. On occasion, the
entire unit is crated for overseas or special shipping conditions. If the unit arrives in a crate, take care when
opening the crate and use all recommended PPE.
WARNING
FAILURE TO USE PROPER EYE PROTECTION OR PERSONAL PROTECTION
EQUIPMENT WHILE OPENING CRATE CAN RESULT IN PERSONAL INJURY.
9.4
Inspecting Equipment
Inspect all goods as received from shipping company BEFORE setting up and operating the shale shaker. Report
a claim for damage or loss immediately to both the carrier and M
‑
I SWACO. Also check bill of lading for any
separately shipped items, including manuals and CDs. Once an order is confirmed as received completed in an
undamaged condition, installation can begin.
10.
INSTALLING / RIG-UP
From delivery, the MONGOOSE PRO requires only minor preparation to install and commission the equipment
for operation.
10.1
Connecting Equipment
The following steps will explain electric and piping connections.
10.1.1
Connecting Vent Hood
The vent hood uses a 10”, 150LB flange connection. Installers should confirm the flange is connected to an air
system capable of pulling 2,000cfm.
10.1.2
Completing Fluid Piping Connections
The carbon steel feeder assembly has an installation guide painted on the rear of the feeder for mounting the inlet
pipe which can accommodate 6”, 8” and 10” inlet pipe sizes (Refer to Figure 12).
1.
Attach the inlet piping to the back of the feeder box. Refer to paragraph 21.4.1 for an overview of the unit’s
piping and instrumentation.
a.
Measure the size of the pipe that will be used to bring drilling fluid to the Shale Shaker.
b.
Cut out the appropriately-sized stencil for the inlet pipe if an opening has not already been made.
c.
Connect the pipe to the header box.
2.
Confirm piping connection is free of leaks.