OPERATION MANUAL
3.3 Checking The Power Supply
METALMASTER machines are supplied wired ready to run. Check the specification plate on the
machine to confirm the correct voltage of the power supply.
Check the rotation of the motor is correct.
The machine must be connected to the power only by a qualified and licensed electrician.
Warranty may be voided if it is found that the connection was not carried out by a qualified
electrician.
3.2 MACHINE LEVELING
To set your machine up so that it operates to optimum performance, apply the following procedure
After your guillotine has been anchored to a concrete slab floor, it then needs to be leveled. The
leveling is performed using each of the screws on each pad.(Fig. 3.1). Loosen the hold down bolts
and place a level on the surface of the working table. Tolerances: 1000:0.30mm, for both longitudi-
nal and transverse.
Metal plates need to be placed under each jacking screw to distribute the load. Once level then
tighten the hold down bolts.
Metal Plate
Jacking Screw
The machine must not rest on supports other
than those defined in Fig. 3.1
Fig. 3.1