29
28
7-10 mm
SW 7
COMMISSIONING
WITH TEST
KIT
LOCKS
IN THE
SASH
Adjust the pin position according to the specifications of the profile-specific system folder to ensure proper
rebate air compensation.
The assembly of the components is hereby completed. On pages 29 and 38, the commissioning with /
without Test Kit continues.
3. Connect the power cord to the INSTINCT Test Kit and then connect it to the power supply.
1. Make sure the door is open.
2a. Locks in the frame - connect the INSTINCT system cable for frame-side assembly 6000 mm to the
designated socket on the INSTINCT Test Kit.
2b. Locks in the sash - connect the end of the INSTINCT cable transition to the designated socket on the
INSTINCT Test Kit.
Control:
Output 2 lights up.
In this chapter, all functions of the door are checked before delivery. It is important to follow the order
carefully to avoid unwanted locking of the door.
Work steps in the door frame
4. Height adjustment of the locking pin
Commissioning with Test Kit
!
NOTE
The final adjustment of the striker plate
takes place only during commissioning, as
seen on pages 65 and 66.