Operation and Maintenance Manual of Aerial Work Platform
or getting close to the electric wire. Please keep the safe distance away from the power line and
the power equipment according to the applicable laws and regulations and the description in the
table below.
Voltage
Required clearance
0-300V
Do not touch
300V-50KV
3.05m
50KV-200KV
4.6m
200KV-350KV
6.10m
350KV-500KV
7.62m
500KV-750KV
10.67m
750KV-1000KV
13.72m
2)
Please consider the influence to the displacement of platform and swinging & relaxation of electric
wire by the strong or gust.
3)
Please stay away from the machine if it contacts by a live electric wire. Do not touch or operate the
machine on the ground or the platform before cutting off the power supply.
4)
Do not operate the machine in the lightning or rainstorm weather.
5)
Do not use the machine as an earth wire in the process of welding.
6) Do not touch charge when charging.
1.8
Tipping-over hazard
The staff, equipment and material on the platform shall not exceed the maximum bearing capacity of the
platform and the extending platform.
Maximum carrying capacity
SS0507
(
S0507SDTCE10
)
Maximum number of people
For indoor use only
:
2 persons
Maximum working load of platform
230kg
Maximum working load of extending platform
113kg
1.9 Safety of workstation
1)
The platform can be lifted on a solid and flat ground only.
2)
The running speed in case of the platform being lifted shall be no more than 0.5km/h.
3)
Do not use the tilting alarm as a level indicator. The tilting alarm of chassis and platform only
alarms when the machine is severely tilted.
4)
In case the tilting alarm sounds: lower the platform and move the platform to a horizontal ground.
In case the tilting alarm sounds when lifting the platform, pay special attention to lower the
platform.
5)
In case the machine is used outdoor, do not lift the platform when the wind speed is above
12.5m/stiff the wind speed exceeds the limit after lifting the platform, please immediately lower the
platform and stop the machine operation.
6)
The ambient temperature for use of this machine is -20
℃
to 40
℃
.
7)
The relative humidity for use of this machine shall be greater than 90% (at 20
℃
).
8)
The allowable voltage fluctuation of the machine is ±10%.
9)
Do not operate the machine under strong wind or gust. Do not increase the surface area of
platform or load. Increase of exposure area in wind will reduce the stability of machine.
3
Содержание S0507SDTCE10
Страница 5: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 1 Safety 1...
Страница 11: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 2 Legend 7...
Страница 12: ...Operation and Maintenance Manual of Aerial Work Platform 8...
Страница 14: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 3 Label 10...
Страница 15: ...Operation and Maintenance Manual of Aerial Work Platform 11...
Страница 16: ...Operation and Maintenance Manual of Aerial Work Platform 12...
Страница 18: ...Operation and Maintenance Manual of Aerial Work Platform 14...
Страница 19: ...Operation and Maintenance Manual of Aerial Work Platform 15...
Страница 21: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 4 Specification 17...
Страница 24: ...Operation and Maintenance Manual of Aerial Work Platform 20...
Страница 25: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 5 Controller 21...
Страница 37: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 6 Emergency operation 33...
Страница 40: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 7 Pre operation inspection 36...
Страница 43: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 8 Workstation inspection 39...
Страница 45: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 9 Function test 41...
Страница 49: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 10 Operation notice 45...
Страница 53: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 11 Transport and lifting instruction 49...
Страница 56: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 12 Maintenance 52...
Страница 76: ...Operation and Maintenance Manual of Aerial Work Platform Chapter 13 Schematic diagram 72...
Страница 77: ...Operation and Maintenance Manual of Aerial Work Platform Electric schematic diagram 73...
Страница 78: ...Operation and Maintenance Manual of Aerial Work Platform Hydraulic schematic diagram 74...