OPERATION
The following paragraphs give the procedures to follow for the proper loading and operation of
the case.
Loading
Merchandise should not be placed in the fixture until all controls have been adjusted and the case
is at the proper temperature.
AT NO TIME SHOULD THE CASE BE STOCKED BEYOND
THE LOAD LINE OR OVER THE FRONT EDGE OF ADJUSTABLE SHELVES.
Do not place product in cases until it is at proper operating temperature. Air discharge and return
flues must remain open and free of debris or obstruction at all times to provide proper
refrigeration and air current performance. Do not allow any product, signs, debris, etc. to block
these grilles. Do not use any non-approved shelving, display racks or any accessory that could
hamper air current performance.
Do not walk on top of the cases!
This could result in damage to the case and serious personal
injury could occur. These cases are not designed to support excessive external weight.
Normal
Operation
During normal operation of the case the case will perform as described in the Installation and
Operation Manual for Parallel Compressor Units, Manual Part Number 31E08001. For single
compressor units, refer to the Installation and Operation Manual for that compressor.
Off-Cycle
Defrost
Off-time defrost is standard on these models. The fans run continuously and defrost termination
is by time (fail-safe). Recommended off-cycle defrost is four (4) per 24 hours with a 40 minute
fail-safe.
Electric Defrost Models
For optional electric defrost, electric heaters are utilized to melt the frost and ice on the coil. The
heaters are located in the air stream in front of the coil. The defrost cycle is time initiated and
should be temperature terminated. Case fans operate continuously in defrost and refrigeration.
As a safety precaution, a safety cutoff Klixon is wired in series with the defrost heater to turn the
heater off at temperatures above 70°F. Recommended electric defrost is four (4) per 24 hours
with a 30 minute fail-safe.
50
Содержание 6RLG3
Страница 3: ...2 6 2006 2 Addendum Ballast Relocation 2 ...
Страница 5: ...2 6 2006 4 Addendum Ballast Relocation Wiring Diagram Both Canopy and Raceway 4 ...
Страница 6: ...2 6 2006 5 Addendum Ballast Relocation Wiring Diagram for Canopy Light 5 ...
Страница 9: ...Plan Views and Cross Sections D6L D6 D6H 8 ...
Страница 10: ...D6RL D6R 9 ...
Страница 11: ...QD6 10 ...
Страница 12: ...HQD6 8 11 16 44 1 16 39 11 16 4 23 5 8 6 80 9 16 43 1 8 32 1 16 59 13 16 50 1 16 22 15 5 8 L OAD LIMIT 11 ...
Страница 34: ...D6 Electrical Model Table QD6 1 3 04 Through D6H 1 3 6 UNIT INSTALLATION 33 ...
Страница 35: ...D6 Electrical Model Table D6H 1 3 6 Through D6R 1 3 4 UNIT INSTALLATION 34 ...
Страница 36: ...D6 Electrical Model Table D6R 1 3 4 Through D6RL G 1 6 UNIT INSTALLATION 35 ...
Страница 39: ...Wiring Diagram UNIT INSTALLATION 38 ...
Страница 40: ...Wiring Diagram Canopy One 1 and Two 2 Light Rows UNIT INSTALLATION 39 ...
Страница 41: ...Wiring Diagram Canopy Two 2 and Three 3 Light Rows UNIT INSTALLATION 40 ...
Страница 42: ...Wiring Diagram Canopy Two 2 Light Rows and Nose Light UNIT INSTALLATION 41 ...
Страница 43: ...Wiring Diagram Off Cycle Defrost UNIT INSTALLATION 42 ...