DS200 Installation Guide
DS200 Installation Guide
DS200 Installation Guide
DS200 Installation Guide
V003. 25.06.2002
B-8
9) Each rack comes as the power card-backplane connection has been made as factory
default. There are special cables that are used for this purpose. In case it is necessary,
those cables can be detached and the two cards can be separated or they can be
combined again, with those cables.
10) Then, you are supposed to make the power connection among the racks. In order to
connect the BPL200-SPS backplanes:
a) For the connection of the BPL200-SPS backplanes of the first and second racks, first
attach the BPLSPS-FC (5-wire cable) to the inter-rack SPS connector that is on the
BPL200-SPS backplane of the first rack.
b) Then, extend the free end of the cable through the holes of the metal plates that are
at the back of the first and the second racks and then attach it to the inter-rack SPS
connector that is on the BPL200-SPS backplane of the second rack. Repeat the same
procedure for the connection between the second and the third racks. See Figure – 2.
11) Attach the 230 VAC cable to the connector on the SPS200. First, make sure that the on/off
switches are off and the fuses are free from any defect. Then, attach the other end of the
cable to one of the plugs next to the mains switch that is at the lower front section of the
cabinet, by extending it through the back of the cabinet.
Two 2A T-type fuses that are necessary for 230 VAC are in the drawer-type compartment
next to the 230 VAC input.
!
VENTS OVER THE CABINET FANS MUST NOT BE COVERED BY ANY
MEANS DURING OPERATION OF THE SYSTEM. CERTAINLY CHECK
WHETHER THE FANS WORK PROPERLY, AT THE TEMPERATURES OVER
20°C.
CAUTION!
The rules that must be obeyed strictly while powering the system on and off are stated as a
special chapter at the end of this guide.
When the system consists of three or more racks, if it is powered on and off by the battery
switches, then those switches are damaged in time, due to the electric arcs. In order to
prevent this situation, a delayed main battery breaker (10 Ampere 250 V Main breaker) is
included in the system. Control of the electricity provided to the racks from the battery is
maintained by this breaker. Detailed information about this is in Chapter II of this guide.
I.2.C. INSTALLATION OF SYSTEMS WITH FOUR OR
MORE RACKS
Installation of the DS200 system in configurations with four, five or six racks is indeed a step
that follows the cabinet-type installation of the system.
Except the case of the four-rack cabinet that has been designed for the four-rack systems,
since installation cannot be realized with one cabinet for the systems with more than three
racks, first installation of two cabinets are realized so as to distribute the necessary quantity
of racks to those two cabinets.
The crucial point while installing the two cabinets is that they should be located side by side
and they should not be displaced during and after the installation.
!
THE CABLES PROVIDING THE CONNECTION BETWEEN THE CABINETS
MAY BE DAMAGED IN CASE OF A DISPLACEMENT.