1.
Provide pressure monitoring in the inlet and outlet lines:
n
As near as possible to the pump. In doing so, maintain the limit values
(
pump data sheet)
2.
Include temperature measurement on the pump side.
3.
Include dry operation protection.
NOTICE!
Damage of the mechanical seal!
–
Prevent uncontrolled turning of the pump for pumps without
sealing system and cleaning temperatures over 80 °C.
1.
Provide CIP cleaning of the pump and lines.
2.
For pumps without sealing system and cleaning temperatures over 80 °C:
Prevent turning of the pump during SIP sterilisation.
3.
Provide fittings for draining the pipelines.
5.6.7 Using hose lines
Observe the manufacturer's instructions.
When using hoses, make sure that the following requirements are met:
n
Hose is suitable for the conveyed medium and pressure,
n
hose in the inlet line is suitable for suction operation,
n
heed minimum bending radius, no kinks,
n
no tensile stress,
n
hose does not twist,
n
do not guide hose over sharp edges or rough surfaces,
n
use supports for long free hose ends.
5.7 Connecting pipelines
Connections for inlet, outlet, drainage pipe and auxiliary pipes
dimensioned drawing.
NOTICE!
Damage to pumps, hoses and fittings with pressure testing or
rinsing!
–
When carrying out pressure tests or rinsing: Do not expose
pumps, hoses or fittings to impermissible pressure.
–
Separate pumps, hoses or fittings from the system in advance if
necessary.
Enabling measurement of the operating
modes
CIP/SIP cleaning
Installation and connection
Type SLH-4G, SLHS-4G
43
01/2016 JPB Rev. 5