26
Vanguard L -
Installation & Servicing
INSTALLATION
24 CASING ASSEMBLY
Vanguard L 4500 TO 7000
The boilers 4500 to 7000 are supplied with the casing already
mounted, therefore the assembly of the panel board, to proceed
in the following way:
Refer to diagram below for details.
A.
Get off the two RH side upper walkways (pos 1 and 2).
B.
Attache the box to the instrument panel support bracket on the
right side of the boiler.
C.
Remove the bottom cover, pos. 4, out of the box support of
the instrument panel.
Fix the instrument panel (pos. 5) to the support pos. 3.
D.
After removal of the two side screws from the panel board,
rotate its cover towards the front and insert the cables and the
capillaries of thermometer and thermostats through the slots
on its base. Insert the capillaries of the thermostats in the pipe
foreseen for their passage that is found under the casing (see
detail “A”).
Pay particular attention when unrolling the capillaries and
insert the bulbs in the two bulb holders, inserting the contact
springs and stopping the capillaries with the lock springs.
E.
After making the electrical connections, replace the instrument
panel and replace the bottom cover of the box support.
F.
Replace the two walkways above.
INST
ALLA
TION
Содержание Vanguard L 340
Страница 37: ...37 Vanguard L Installation Servicing NOTES...
Страница 38: ...38 Vanguard L Installation Servicing NOTES...
Страница 39: ...39 Vanguard L Installation Servicing NOTES...