Viceroy GTS - 

Installation & Servicing

GENERAL

Air inlet

B

Air outlet

550 mm

1.5 m

1 m

*

1 m

*

A

C

vic9106

Refer to notes above

Refer to notes above

2  BOILER CLEARANCES

The minimum dimensions as indicated must be respected to 

ensure good access around the boiler.

Note. 

To allow the inlet of the combustion air, the boiler room 

must be adequately ventilated, the section and the location of 

which must comply with local recommendations.

Refer also to Frame 3.
The boiler must be positioned so that there is enough space 

available to allow the following:

• 

Access around the boiler for servicing.

• 

Space to open the boiler front door.

• 

Space to access the burner.

Recommended minimum clearances are as follows:

Rear

  1000mm or adequate space to make the flue connections 

and access to the flue sample point, drain connection, flue 

and smokehood cleanout doors and any safety or control 

devices.

Sides

  One side may be 100mm the other side must be 200mm 

plus the burner projection or 500mm whichever is the 

greater to allow the burner door to be swung open and 

maintain access to the rear.    In multiple boiler installations 

both sides may be 100mm except at one end consideration 

must also be given to the burner door hinge position and 

consequent clearance for access to the rear.

Front

  See Table below.

567

R = 41

5

R = 751,

5

15

240

burner door open

View from top

R = 751.5

vic7084

  GTS 8 

GTS 9 

GTS 10 

GTS 11 

GTS 12 

GTS 13 

GTS 14

 

1505  1665  1825  1985  2145  2305 2465

 105 

105 

105 

105 

105 

105 

105

 1500 

2000 

2000 

2000 

2500 

2500 

2500

A
B
C

Dimension

Boiler

mm
mm
mm

Содержание VICEROY GTS 8

Страница 1: ...y and performance speci cation that we require Do not use reconditioned or copy parts that have not been clearly authorised by Ideal For the very latest copy of literature for speci cation and mainten...

Страница 2: ...s 8 9 10 11 12 13 14 Maximum kW 390 450 540 600 670 720 780 Heat Output Btu hx103 1330 1535 1842 2047 2286 2457 2661 Minimum kW 300 390 450 540 600 670 720 Heat Output Btu hx103 1024 1330 1535 1842 20...

Страница 3: ...lers are a range of cast iron sectional pressure jet boilers offering high efficiency operation ease of maintenance fuel flexibility and low emissions Suitable for oil or gas operation the Viceroy GTS...

Страница 4: ...r heating boilers for atomizing oil burners 73 23 EEC Low voltage directive Relevant standard is EN60335 1 89 336 EEC Electromagnetic Compatibility Directive Relevant standards are EN50081 1 EN50082 1...

Страница 5: ...or even premature boiler failure Corrosion and the formation of black iron oxide sludge will ultimately result in premature radiator failure Open vented systems are not completely sealed from the atm...

Страница 6: ...2305 2465 2625 2785 L 1505 1665 1825 1985 2145 2305 2465 S 1183 1343 1503 1663 1823 1983 2143 F 127 5 127 5 127 5 127 5 127 5 127 5 127 5 G 130 130 130 130 130 130 130 H 105 105 105 105 105 105 105 K...

Страница 7: ...learances are as follows Rear 1000mm or adequate space to make the flue connections and access to the flue sample point drain connection flue and smokehood cleanout doors and any safety or control dev...

Страница 8: ...s IMPORTANT The use of an extractor fan in the same room as the boiler or in an adjacent communicating room can in certain conditions adversely affect the safe operation of the boiler Where such a fan...

Страница 9: ...the output of the boiler see table below Working pressure 6 bar maximum Particular reference should be made to BS 6644 Section 2 Subsection 11 and Guidance note PM5 Automatically controlled steam and...

Страница 10: ...f the overheat thermostat If system return temperature remains below 30 C for most of the heating period some protection from condensation is required Please contact Ideal Boilers for further informat...

Страница 11: ...tor 6 Automatic venting valve 7 Valve 8 Shunt pump required for all models 9 Expansion tank 10 Draining valve 11 Sludge valve 12 Mixing valve 13 Non return valve 14 Heating pump 15 Low water safety pr...

Страница 12: ...ach boiler model in order to ensure sufficient draught at the outlet 1 at boiler maximum input 2 Boiler flow temperature 80 C ambient temperature 20 C 11 DIMENSIONAL INFORMATION REQUIRED FOR THE FLUE...

Страница 13: ...The tables below show the numbers of the packages which make up the boiler The packages are listed in the order in which they are opened for assembly Tools required not supplied 12mm allen key Cross...

Страница 14: ...e fabric to top packs IE 51 to IE 57 Adapt length if necessary or fold the lower insulation after the casing has been completely assembled 15 POSITIONING THE REAR SECTION 1 Determine the required loca...

Страница 15: ...me The arrow marker points to the rear to denote the correct way to fit the section 2 Fit the connections of the special intermediate section onto the nipples in the rear section 3 Ensure that the the...

Страница 16: ...mbly rods in the order given in the diagram in the same manner 5 Remove the assembly tool Lg 580 Lg 580 Lg 420 Lg 580 Lg 420 Lg 420 Lg 580 Lg 580 Lg 580 Lg 580 Lg 740 Lg 420 Lg 740 Lg 740 Lg 740 Lg 74...

Страница 17: ...pply water 8 Connect the pressure system water 9 Open the fill valve 10 Pressurise the boiler Maintain pressure for 30 minutes Any drop in pressure indicates a leakage in the boiler body 11 After succ...

Страница 18: ...urn flanged tail pipes using four M16 nuts for each flange with a gasket as shown Note A The flow tail pipe outlet must face upwards to accommodate the flow switch B The return flange for models GTS11...

Страница 19: ...k on the left or the right according to the direction in which the door will be opened and fix using three M12x30 bolts and washers 6 Fix the burner door guide bracket body accessories pack using two...

Страница 20: ...10 Viceroy GTS 11 12 Viceroy GTS 13 14 pack IE 30 pack IE 31 pack IE 32 pack IE 33 Upper 8229 0010 2x8229 0010 then then 8229 0022 2x8229 0010 1x8229 0022 3x8229 0010 Middle 8229 0011 2x8229 0011 then...

Страница 21: ...each strap to the lower casing support at each side of the boiler Note The table below indicates the quantity of insulation panels supplied for each boiler and the appropriate position according to th...

Страница 22: ...lock washer at each support 2 Fit the cross pieces using two M5x12 bolts and lock washer 3 Fit the front top panel and secure to the wiring ducts using M5x12 bolts and lock washers 29 INSTALLING THE M...

Страница 23: ...ng screws and shakeproof washers provided 6 Pull the mains cable and any other sensors into the control panel through the appropriate opening ready to make the connections Front Rear vic7105 3 4 5 vic...

Страница 24: ...e below 2 Fix the first intermediate top cover length 480 onto the wiring duct using four M5x12 bolts and lock washers 3 Fix the remaining top covers onto the wiring duct using two M5x12 bolts and loc...

Страница 25: ...and lock washer and onto the rear top cover using two self tapping screws and lock washers 5 Hook the lower rear panel onto the two screws on the middle panel and tighten these screws 6 Secure using t...

Страница 26: ...ons 2 Hook the front casing support two slots into the side panel slots 37 NAMEPLATE 1 Affix the identification plate supplied in the instructions bag on the casing on the left or right hand side in a...

Страница 27: ...ONNECTIONS 1 To gain access to the connection strip unscrew the three screws on the rear of the control panel and open the panel 2 Pass the connecting cables to the control panel through the two cut o...

Страница 28: ...T8 S3 5 BA 4 2 L BA 3 BA 6 BA 7 BA 8 BA 9 BA 10 BA 11 BA 12 B Burner BA Connection strip DJ10A 10A circuit breaker L Live N Neutral TCH1 Stage 1 boiler thermostat TCH2 Stage 2 boiler thermostat TS1 Sa...

Страница 29: ...the burner exceed the following values start up current 16 A or Max Power 450 W or 1 2 cont hp motor or Max Current 2A cos 0 7 The burner controls circuit must use a relay Burner Wire Connector No Fro...

Страница 30: ...must have been carried out on them in accordance with the instructions for the domestic hot water calorifier if existing and boiler Refer to the following instructions and Frame 48 to start up the bo...

Страница 31: ...r specific operating features 10 Set the boiler thermostats 3 to the appropriate settings ensuring the second stage is 5 C lower than the first stage if a 2 stage burner is fitted 49 GENERAL CHECKS Ma...

Страница 32: ...ombustion chamber four nuts and flue way three nuts doors by removing the nuts 6 Remove the flue way baffles 7 Thoroughly clean the flue ways and baffles 8 Release and allow to swing down the rear cle...

Страница 33: ...ith the system hot examine all water connections for soundness Check the gas rate and measure the combustion CO CO2 content Complete the boiler log book Carry out functional checks as appropriate 55 S...

Страница 34: ...34 Viceroy GTS Installation Servicing NOTES...

Страница 35: ...35 Viceroy GTS Installation Servicing NOTES...

Страница 36: ...2 Ideal is a trademark of Ideal Boilers Registered Office Ideal Boilers Ltd PO Box 103 National Avenue Kingston Upon Hull HU5 4JN Tel 01482 492251 Fax 01482 448858 Registration No London 322 137 Ideal...

Отзывы: