33
Buccaneer GTE -
Installation & Servicing
INSTALLATION
buc5543
P
3/4"
55 INSTALLING THE FEET
buc5541
-
Screw the 4 adjustable feet (delivered in the hot water
calorifier instruction pack) on the bottom of the tank.
56 LEVELLING THE TANK
-
Level the tank by adjusting its feet.
Basic height 35mm, adjustment range 35-40mm.
19
buc5542
57 ASSEMBLING THE BOILER ON THE HOT WATER CALORIFIER
-
Locate the boiler on top of the hot water calorifier,
ensuring accuracy of dimension P at the front.
-
The boiler can be lifted using two 3/4" tubes placed as
shown.
-
Screw the adjustable boiler feet all the way in to the
minimum position (25mm).
Boiler
GTE 4/L160
Model
GTE 5/L160 - L250
GTE 6/L160
GTE 6/L250
P
(mm)
256
136
COMBINA
TION BOILERS COMBINA
TION BOILERS
Содержание Buccaneer GTE 5
Страница 1: ......
Страница 38: ...38 Buccaneer GTE Installation Servicing NOTES...
Страница 39: ...39 Buccaneer GTE Installation Servicing NOTES...