TEST PROCEDURE
Test 18: Check voltage between connector
CN-88 (2) - GND.
Disconnect connector CN-88 from power
max solenoid valve.
Start switch ON.
Check voltage as figure.
(1)
①
②
③
2)
Test 19: Check resistance of the solenoid
valve between CN-88 (1)-(2).
Starting switch OFF.
Disconnect connector CN-88 from power
max solenoid valve.
Check resistance as figure.
(2)
①
②
③
LH RCV lever
Power max switch
Power max
solenoid valve
CN-88
Multimeter
1
2
1
2
130ZF6MS15
LH RCV lever
Power max switch
Power max
solenoid valve
CN-88
Multimeter
1
2
1
2
GROUND
SPEC : Starting switch ON : 24
±
1V
Starting switch OFF : 0V
SPEC : 15~35
Ω
130ZF6MS14
Содержание HX130 LCR
Страница 11: ...1 1 SECTION 1 GENERAL Group 1 Safety Hints 1 1 Group 2 Specifications 1 10 ...
Страница 174: ...4 5 MEMORANDUM HYUNDAI HEAVY INDUSTRIES CO LTD CONSTRUCTION EQUIPMENT DIV ...
Страница 218: ...4 49 4 49 No of pin Receptacle connector female Plug connector male 14 1 7 6 14 MG610406 KET SDL CONNECTOR 13 ...
Страница 517: ...8 89 Insert O rings to the relief valve 30 and reassemble them to rear cover 20 This completes assembly 17 32038SM42 ...
Страница 536: ...8 108 125LCR8TM30 Turn casing 1 upside down and remove oil seal 3 using jig 29 ...
Страница 545: ...8 117 125LCR8TM61 After assembling spring 44 in order clamp plug 41 Tightening torque 5 5 0 5 kgf m 39 8 3 6 lbf ft 31 ...
Страница 566: ...8 138 Remove lock nut 22 and then boot 23 14 36078RL14 2507ARL10 ...
Страница 577: ...8 149 14 15 3 Install cover 3 to body 1 and tighten bolts 14 Torque 10 12 5 kgf m 72 3 90 4 lbf ft 7 21078DA10 ...
Страница 609: ...8 181 1 STRUCTURE GROUP 11 WORK EQUIPMENT SECTION C SECTION B SECTION A 130ZF8DA44 SECTION A SECTION B SECTION C ...