INSTALLATION MANUAL
Page 4 of 15
HUBER+SUHNER disclaims any liability resulting from incorrect installation and use, including any damages resulting from the use of tools and
accessories other than the ones recommended herein. Any installation performed by unqualified personnel voids the product warranty provided by
HUBER+SUHNER. All due care and attention must be exercised when performing the installation of these products. For advice concerning the
general handling of these products please contact HUBER+SUHNER.
Step 6
Fix the cable to the mast using HUBER+SUHNER clamps,
which are available for different profiles. Recommended spacing
between the clamps is 1m.
Clamps should be applied to hybrid cable starting from a point
0.5m to 1.0m below the cable entry proceeding down to the
bottom of the mast. The cable must be straight and in line with
the MLEH enclosure between the cable entry and the first cable
clamp. The maximum allowed misalignment is 5°, or 5 cm at 0.5
m below the cable entry.
The recommended spacing between the clamps is 1 m.
Minimum bending radius of the cable is 10x cable diameter.
Do not remove the rope before all cable clamps
are mounted.
Step 7
Remove the rope from the cable hoist after all cable clamps are
mounted.
Remove the blue braided tube.
Step 8
The MLEH enclosure has an integral earth point suitable for M8
lug for grounding. Connect the earth point to an earth bar with a
grounding assembly with minimum 16mm
2
/ 6 AWG cross
section. Consider the correct order: first the grounding wire lug,
secondly the washer, thirdly the spring washer.
Tighten the M8 earth screw with a torque of
5 Nm. Be careful not to damage the enclosure by
tightening the M8 earth screw too tightly.
HUBER+SUHNER offers different grounding assemblies:
Item no. 85086667: 0.5m, black, 16mm
2
, 2x M8 lug
Item no. 85083781: 0.5m, yellow/green, 16mm
2
, 2x M8 lug
Item no. 85086668: 0.5m, black, 25mm
2
, 2x M8 lug
Item no. 85083792: 0.5m, yellow/green, 25mm
2
, 2x M8 lug