Step 2 Check that the cable length is appropriate.
Step 3 Check that the cables around the connectors are not twisted.
Step 4 Check that cables are routed as required.
Step 5 Check that the power cables, multi-port cables, and network cables are properly
connected. For details, see
Table 4-5 Cable connection checklist
Item
Description
Power cables
● All power cables are properly connected to power
supply units (PSUs).
● Power cables are securely connected.
Multi-port cables
● Multi-port cables are properly connected to the
universal connector ports on server nodes.
● Multi-port cables are securely connected.
Network cables
Network cables are correctly connected to the specified
management or service network port.
----End
4.6.3 Powering On the Chassis
Scenario
Devices and cables are properly installed.
Procedure
Step 1 Switch on the AC power distribution box (PDB) that corresponds to the power
cable of the chassis.
Step 2 Switch on the busbar of the cabinet.
Step 3 Observe the status of chassis indicators.
The chassis is properly powered on if the following indicators are steady green:
●
Operating status indicator on each PSU
●
Power indicator on the server front panel
----End
4.6.4 Checking Device Operating Status
Procedure
Step 1 Power on the chassis. For details, see
TaiShan X6000 Server
User Guide
4 Installing the X6000
Issue 04 (2020-06-05)
Copyright © Huawei Technologies Co., Ltd.
57