UPS5000-E-(25 kVA-75 kVA)-SM
User Manual (Half Height)
3 Installation
Issue 03 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
72
Countersunk Head Screw 2 should be installed on the hinges of the door frame as shown in the
figure.
----End
3.3.2 Connecting Power Cables
Procedure
Step 1
Ground each UPS.
Step 2
Connect input power cables to each UPS.
Step 3
Connect output power cables to each UPS.
Step 4
Connect battery cables to each UPS.
Step 5
Choose a parallel mode and connect cables to the parallel system based on site requirements.
show the typical conceptual diagram and cable connections for a
1+1 parallel system.
Figure 3-39
Conceptual diagram of a 1+1 parallel system