12. Install the chassis into the rack.
13. Connect all peripheral cables to the servers and chassis.
14. Connect each power cord to the chassis.
15. Connect each power cord to the power source.
The installation is complete.
Installing an energy pack in a chassis using the 1800 W–2200 W power supply
Prerequisites
Before you install this option:
• Make sure that a Smart Array P-class Gen10 controller is installed in the server.
For more information, see the server user guide on the Hewlett Packard Enterprise website (
• Make sure that you have the following items available:
◦
Controller backup power cable (ships with the controller)
◦
Energy pack option
◦
If not yet installed, the energy pack holder from the HPE r2x00 Gen10 1800 W–2200 W Redundant Power Supply
Unit Enablement Kit (PN 880189-B21)
◦
T-10 Torx screwdriver
Procedure
1.
2.
Remove all power:
Hardware options installation