Ground Bonding kit 55
From the rack to a building facility
, contact your building supervisor for more information. The following
figure illustrates parts for this step.
Reference Item
1
48.26-cm (19-in) mounting rail (the mounting hole is
located at the top or bottom of the rail)
2
M8 hex nut
3
M8 Belleville toothed washer
4
Facility ground (not included with this kit)
5
M8 x 20 bolt
Installing the ground bonding rack option kit on HP 10000 G2
Series Rack side panels
From the middle system chassis rail to the bottom side panel:
1.
Connect a 36.83-cm (14.5-in) and a 15.24-cm (6-in) grounding strap with connectors together.
2.
Insert a T-25 Torx screw through the end of the 36.83-cm (14.5-in) grounding strap, and secure it to the
middle system chassis rail.
3.
Place the end of the 15.24-cm (6-in) grounding strap over the grounding lug on the bottom side panel.
4.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the bottom
side panel and tighten.
Содержание HP 10000 G2 Series
Страница 35: ...Cable Management Bracket kit 35 Installation is complete ...
Страница 41: ...Cable Management Tray kit 41 4 Route the cables through the cable management tray Ground bonding stud location ...
Страница 74: ...Hook and Loop Cabling Strap Clip kit 74 ...
Страница 75: ...Hook and Loop Cabling Strap Clip kit 75 Installation is complete ...
Страница 104: ...Rack Air Duct kit 104 For more information see Baying kit on page 25 ...
Страница 125: ...Vertical PDU Mounting kit 125 HP monitored PDU 2 Install the PDU The installation is complete ...