Chapter 4
Cabling and Power Up
Voltage Check
43
Voltage Range Verification of Receptacle
This measures the voltage between L1 and L2, L1 to ground, and L2 to ground. Three separate
measurements are performed during this procedure. See Figure 4-1 for voltage reference points
when performing the following measurements.
Figure 4-1 Voltage Reference Points for IEC 320 C19 Plug
IMPORTANT
These measurements must be performed for every power cord that plugs into the HP
9000 rp7420 Server.
Step 1.
Measure the voltage between L1 and L2. This is considered to be a phase-to-phase measurement in
North America. In Europe and certain parts of Asia-Pacific, this measurement is referred to as a
phase-to-neutral measurement. The expected voltage measured should be between 200–240 V AC
regardless of the geographic region.
Step 2.
Measure the voltage between L1 and ground. In North America, verify this voltage is between
100–120 V AC. In Europe and certain parts of Asia-Pacific, verify this voltage is between 200–240 V
AC.
Step 3.
Measure the voltage between L2 and ground. In North America, verify this voltage is between
100–120 V AC. In Europe and certain parts of Asia-Pacific, verify this voltage is 0 (zero) V AC.
Table 4-1 provides single phase voltage measurement examples dependent on the geographic region where
these measurements are taken.
Table 4-1
Single Phase Voltage Examples
Japan
North
America
Europe
a
a. In some European countries there might not be a
polarization.
L1-L2
210 V
208 V or 240 V
230 V
L1-GND
105 V
120 V
230 V
L2-GND
105 V
120 V
0 V
Содержание 9000 rp7420
Страница 4: ...Contents iv Index 67 ...
Страница 6: ...Tables vi ...
Страница 8: ...Figures viii ...
Страница 74: ...Chapter 4 Cabling and Power Up Using the Checklist 66 ...
Страница 76: ...Index 68 U unpacking inspecting for damage 12 V verifying system configuration 61 voltage check 46 ...