Ground Bonding kit 53
2.
Place the other end of the same grounding strap over the grounding lug on the rack top.
3.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the rack top,
and then tighten the washer.
From the grounding lug on the rack top to the grounding lug on the perforated panel:
1.
Place one end of a 36.83-cm (14.5-inch) grounding strap over the grounding lug on the rack top.
2.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the rack top,
and then tighten the washer.
3.
Place the other end of the same grounding strap over the grounding lug on the perforated panel.
4.
Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the perforated
panel, and then tighten the washer.
From the grounding lug on the perforated panel or fan kit to the grounding lug on the egress slot:
1.
Place one end of a 15.24-cm (6-inch) grounding strap over the grounding lug on the perforated panel
or fan kit.
Содержание 669048-009
Страница 39: ...Cable Management Bracket kit 39 Installation is complete ...
Страница 45: ...Cable Management Tray kit 45 4 Route the cables through the cable management tray Ground bonding stud location ...
Страница 60: ...Filler Panel kit 60 ...
Страница 68: ...Hook and Loop Cabling Strap Clip kit 68 ...
Страница 69: ...Hook and Loop Cabling Strap Clip kit 69 Installation is complete ...