Airflow Optimization kit 24
Airflow Optimization kit
About this device
The Airflow Optimization kit enables you to install foam rail gaskets in your HP Advanced Series Racks and
Enterprise Series Racks 36U, 42U, and 47U 600-mm (24-in) wide racks and in to 42U 800-mm (31-in) wide
racks to improve separation between hot and cold aisles in the data center.
Kit contents
Item
Quantity
Foam rail gasket roll
4
600-mm (24-in) perforated floor
gasket
—or—
800-mm (31-in) perforated floor
gasket
1
Extra hardware might be included for your convenience.
Required tools
No tools are required for this procedure.
Installing foam rail gaskets between racks
CAUTION:
The foam rail gasket must be installed into the rack before two or more racks can be
bayed together. For additional information on baying racks, see the
HP Baying Rack Option Kit
.
If installing the foam rail gasket between racks that have a baying kit installed, the baying bracket must be
removed before the foam rail gasket can be inserted between the racks.
1.
Position the racks side by side.
2.
Cut the foam rail gasket to fit the size of your rack.
Содержание 669048-009
Страница 39: ...Cable Management Bracket kit 39 Installation is complete ...
Страница 45: ...Cable Management Tray kit 45 4 Route the cables through the cable management tray Ground bonding stud location ...
Страница 60: ...Filler Panel kit 60 ...
Страница 68: ...Hook and Loop Cabling Strap Clip kit 68 ...
Страница 69: ...Hook and Loop Cabling Strap Clip kit 69 Installation is complete ...