34
Flush
at peak
Fig. B
ROOF PANELS
PARTS REQUIRED:
Ensure and adjust the spacing between the centers of the rafters.
Measure from gable panels at each end of roof
(Fig. D)
.
Secure rafters with (1) 2" nail into each rafter
(Fig. E)
.
5
3
4
Fig. E
NOTE:
Measurements are from inside of panels
x8
2" (5,1 cm)
24"
(60,9 cm)
24-3/8"
(61,9 cm)
24-3/8"
(61,9 cm)
24"
(60,9 cm)
24"
(60,9 cm)
24"
(60,9 cm)
2" (5,1 cm) Nails
Rafter
Roof Panel
Gable Panel
Fig. C
1/2"
(1,3 cm)
Flush
Rafter
Gable Panel
Fig. D
x1
7/16 x 47-7/8 x 48"
(1,1 x 121,6 x 121,9 cm)
Install the
47-7/8" x 48"
panel flush to the
installed panel and flush at the peak
(Fig. B)
.
Secure panel with (2) 2" nails in the corners.
2 Nails
Step 3
2 Nails
Step 4
47-7/8"x 48"
48"
(121,9 cm)
Move to the opposite end.
Move the panel side-to-side until the top
corner is flush at the peak
(Fig. B)
,
Adjust the front gable panel for the 1/2"
measurement
(Fig. C)
.
Secure panel with (2) 2" nails in the corners.