30
A 12 Order No. BA 93-20-270 Issue 01.03.08
Setting of welding gun A 12
Plunging depth
Lift
Plunging depth
Lift
(metric/mm)
(imperial)
3
#4 or 12 gage
1,0
1,0
2,5
1,5
4
#8
1,0
1,0
2,5
1,5
5
#10 or 3/16"
1,0
1,0
2,5
1,5
6
1/4"
1,0
1,0
2,5
1,5
8
5/16"
1,0
1,0
2,5
2,0
10
7/16"
1,5
1,5
3,0
2,0
12
1/2"
2,0
2,0
3,0
2,5
Eff. diameter
Preferably under shielding gas
Preferably with ceramic ferrule
Welding element with
conical face
Welding element with
conical or
plane face
*)
When welding with shielding gas, a 10% longer time is normally selected.
When welding alloyed steel, a 10% lower current is normally selected.
The given values apply to weldings in the welding position PA. The welding time shall be
reduced for welding in the welding position PC.
In the case of short cycle stud welding, the welding time is less than 100 ms. It depends not
only on the stud diameter, but also on the available current intensity (I[A] = min. 100 x Ø (mm)).
The welding time should be as short as possible in the case of welding without weld pool
protection.
Welding energy is only selected by welding time.
Further notes on
– welding elements
– prestress at installation (tie load) and torque
– material combinations
see appendix and operating manual of the according welding
gun.
Содержание 93-20-270
Страница 1: ...A 12 Welding Gun 93 20 270 Operating Manual ...
Страница 45: ...A 12 Order No BA 93 20 270 Issue 01 03 08 45 Welding gun type A 12 93 20 270 ...
Страница 47: ...A 12 Order No BA 93 20 270 Issue 01 03 08 47 Shielding gas tripod complete A 12 93 40 021 ...
Страница 49: ...A 12 Order No BA 93 20 270 Issue 01 03 08 49 Ceramic tripod complete A 12 93 40 022 ...
Страница 61: ...A 12 Order No BA 93 20 270 Issue 01 03 08 61 Service Support ...
Страница 65: ......