HG2200/HG2200AT Operator’s Manual
Haul
72 - Transport
Tracked Unit
Load Unit
1. Stow mast in horizontal position.
2. Start unit. See “Start Unit” on page 64.
3. Raise stabilizers.
4. Move winch to rear of trailer and align with ramps.
5. Ensure engine is at full throttle and slowly drive unit onto trailer.
6. Lower stabilizers to trailer floor.
7. Stop engine when unit is safely positioned on trailer bed.
8. Attach tiedowns to winch where indicated on “Procedure” on page 72.
Tie Down Unit
Points
Tiedown points are identified by tiedown decals. Securing to trailer at other
points can damage machinery.
Procedure
To tie down unit, use D-rings shown.
j64om017w.eps
Содержание HG2200AT
Страница 1: ...TECHNICAL PUBLICATIONS Operator s Manual HG2200 HG2200AT Issue 2 1 960 1119 Original Instruction...
Страница 51: ...HG2200 HG2200AT Operator s Manual Battery Disconnect 50 Controls...
Страница 75: ...HG2200 HG2200AT Operator s Manual Retrieve Tracked Unit 74 Transport...
Страница 87: ...HG2200 HG2200AT Operator s Manual Finish Installation 86 Burst Pipe...
Страница 129: ...HG2200 HG2200AT Operator s Manual As Needed 128 Service...
Страница 133: ...HG2200 HG2200AT Operator s Manual Declaration of Conformity Information 132 Specifications...
Страница 136: ...HG2200 HG2200AT Operator s Manual Service Record 135 Service Record Service Performed Date Hours...
Страница 137: ...HG2200 HG2200AT Operator s Manual 136 Service Record Service Performed Date Hours...
Страница 138: ...HG2200 HG2200AT Operator s Manual Appendix 137 Appendix Chapter Contents Tire Safety Information...
Страница 146: ......