Installing the Eave Platform Handrails
The following procedure is for the installation of handrails for the eave platform above the eave.
1. Install the handrail brackets (17) to the top end of the handrail posts (9) with flange bolts (2) and
flange nuts (3).
NOTE:
Install the flange bolts (2) from the inside of the platform and flange nuts (3) on the outside.
2. Install the single platform upper handrail (18) to the handrail brackets (17) using two self-drilling
screws (4) per bracket.
NOTE:
Install the self-drilling screw (4) from the outside of the handrail bracket (17).
3. Install the double platform upper handrail (21) to the handrail brackets (17) using two self-drilling
screws (4) per bracket.
IMPORTANT:
Insert the end (smaller diameter) of the double platform upper handrail (21) into the
single platform upper handrail (18) of the first platform section before securing with
the self-drilling screws (4).
NOTE:
Install the self-drilling screw (4) from the outside of the handrail bracket (17).
4. Align the single platform lower handrail (19) with the hole located in the middle of the handrail posts
(9) and secure using self-drilling screws (4).
NOTE:
Install the self-drilling screw (4) from the outside of the handrail post (9).
5. Align the double platform lower handrail (22) with the hole located in the middle of the handrail posts
(9) and secure using self-drilling screws (4).
IMPORTANT:
Make sure to insert the end (smaller diameter) of the double platform lower handrail
(22) into the single platform lower handrail (19) in the first platform section before
securing with the self-drilling screws (4).
NOTE:
Install the self-drilling screw (4) from the outside of the handrail post (9).