Chapter 2: Intermediate Platform
Installing the Wall Attachment Brackets
Four wall attachment brackets are installed on the sidewall for the installation of the intermediate platform
assembly.
1. Align the tenth hole (H) from the bottom of each wall attachment bracket (14) to the seam (K)
between the third ring (I) and the fourth ring (J) of the sidewall.
2. After aligning the tenth hole (H) to the seam, using a bubble level or plumb line, mark and field drill
one hole (top most hole) in the third ring (I) and one hole (bottom most hole) in the fourth ring (J)
where a hole in the wall attachment bracket (14) lines up on a hill.
3. Install standard bin bolts (B) and flange nuts (C) to secure the wall attachment brackets (14) to the
sidewall.
NOTE:
• The bolts must be installed with the bolt head on the inside of the bin.
• Install each wall attachment bracket (14) with the angle open outward, and a hole to hole
gap (F) of 18.75 in.
• Install the outer two wall attachment brackets (14) to the stiffeners in the sidewall.
• Install the inner two wall attachment brackets (14) to the sidewall.
Figure 2-8
Installing the wall attachment brackets
14
Wall attachment bracket (WBS-0010)
H
Tenth hole in horizontal seam
B
Standard bin bolt with sealing washer
I
Third ring of sidewall
C
Flange nut
J
Fourth ring of sidewall
F
18.75 in
K
Seam between third and fourth ring
PNEG-2077
TopDry – Platforms and Bin Stairs
21